Comments: |
Construction is starting to wrap up with all projects anticipating to be complete by May 2024 with the exception of F-35: Construct M&I Facility. That project is working itâs way through the contracting process and should break ground around May 2024. As of 18 Dec 2023, 6 project remain under construction, 1 in contracting acquisition, and 13 are complete. Hauling PFAS soil to the "pile" is complete except for foundations for the M&I facility. Treating soil w/ BAM from ORIN technologies has been determined that it will not allow leaching of PFAS from the soil in a TCLP test. Awaiting Dane County Landfill determination if it will be allowed for daily cover.
F-35 Alter B400 - 80% complete
F-35 3-Bay Hangar - 76% complete
F-35 Construct Sunshades - CT & Dply - 92% complete
F-35 Repair B420 - 13% complete
F-35 ADAL B409 - 70% complete
F-35 Repair B511 Hazmart - 6% complete
F-35 Construct M&I Facility - Construction acquisition
|