For the previous 6 months (1 Jan - 30 Jun 2023) the following activity has taken place for F-35 construction. The below is a list of on-going projects and if they have contributed to the soil management pile.
XGFG189004 - Construct Alert Shelters - Construction on-going, no soil added to pile, no de-watering
XGFG182009 - F-35 Alter B400 AMXS - Construction on-going, no soil added to pile, no de-watering
XGFG192005 - F-35 Repair B511 Hazmart - Construction on-going, no soil/water management needed
XGFG139001 - Medical Readiness Facility - Construction on-going, no soil/water management needed
XGFG189002 - F-35 3-Bay Specialized Hangar - Construction on-going, soil added to pile, no de-watering needed
XGFG182011 - F-35 Repair B510 - Construction on-going, no soil added to pile, no de-watering needed
XGFG182003 - F-35 ADAL B409 - Construction on-going, no soil/water management needed
XGFG182013 - F-35 Construct R-11 Parking - Construction on-going, no soil added to pile, no de-watering needed
XGFG182004 - F-35 Alter B412 - Construction on-going, no soil/water management needed
XGFG182019 - F-35 Repair B420 - Under contract, awaiting construction start
XGFG182053 & XGFG202053 - F-35 Construct Sunshade for CT & Deployed Missions - Under contract, awaiting construction start
|