Reporting Period: | 7/1/2021 - 12/31/2021 |
BRRTS No: | 02-37-587000 |
Activity Name: | CN/WCL RR TRACK FORMER |
Status: | Site Investigation |
Activity: | Report Preparation |
Comments: | Modified Work Plan submitted to WDNR 9/10/2021 WDNR authorization received 9/29/2021 Investigation activities completed 11/12/2021 Analytical report submitted to WDNR 12/15/2021 Site Investigation Report in progress Interim Actions Report submitted to WDNR 9/28/2021 (Southern Lot 2 drainage project) WDNR authorization received 10/15/2021 Southern Lot 2 drainage project completed 12/2/2021 As-Built Report in progress |
Submitted by Trenna Seilheimer on 01/13/2022 |