Comments: |
A Project Manager Change was submitted on August 10. An Aerial Deposition Final Report was submitted on August 11. A Conceptual Site Model was submitted on August 11. A Site Investigation Work Plan was submitted on September 21. A Project Manager Change was submitted on September 25. A Q3 2020 Project Status report was submitted on October 15. A request to hold review of the September 25 Site Investigation Work Plan was submitted on November 11. Routine communications were completed with the WDNR regarding the investigation activities.
|