2024-01-14
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2023 - 12/31/2023
|
|
2023-07-14
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 01/01/2023 - 06/30/2023
|
|
2023-01-20
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2022 - 12/31/2022
|
|
2022-07-22
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2022 - 6/30/2022
|
|
2022-01-22
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2021 - 12/31/2021
|
|
2021-07-29
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2021 - 6/30/2021
|
|
2021-06-04
|
36
|
Site Investigation Workplan (SIWP) Approved
|
|
ADDITIONAL SOIL SAMPLING AND ONE ROUND OF GROUNDWATER MONITORING
|
|
2021-04-19
|
135
|
Site Investigation Workplan (SIWP) Received (fee)
|
|
|
|
2021-04-06
|
130
|
DNR Regulatory Reminder Sent
|
|
VAPOR INTRUSION AND TCE REMINDER LETTER
|
|
2021-02-22
|
80
|
Closure Not Recommended
|
|
ADDITIONAL GW & SOIL SAMPLING REQUIRED
|
|
2021-01-24
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2020 - 12/31/2020
|
|
2020-10-01
|
118
|
PFAS Sampling Not Required At This Time
|
|
COMPLETED AS PART OF CLOSURE NOT RECOMMENDED PEER REVIEW
|
|
2020-08-17
|
130
|
DNR Regulatory Reminder Sent
|
|
EMERGING CONTAMINANTS REMINDER LETTER
|
|
2020-08-12
|
99
|
Miscellaneous
|
|
DHS PFAS NOTIFICATION PROTOCOLS
|
|
2020-08-07
|
79
|
Case Closure Review Request Received
|
|
AUTO-ENTERED
|
|
2020-08-07
|
114
|
PFAS Scoping Statement Received
|
|
EC SCOPING RECEIVED WITH CLOSURE REQUEST
|
|
2020-07-30
|
779
|
Case Closure Review Fee Received
|
|
|
|
2020-07-30
|
710
|
Database Fee Paid for Soil Continuing Obligation(s)
|
|
|
|
2020-07-27
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2020 - 6/30/2020
|
|
2019-09-20
|
99
|
Miscellaneous
|
|
CLARIFICATION REGARDING ADMINISTRATION OF REMEDIATION ACTIVITIES
|
|
2019-01-04
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2018 - 12/31/2018
|
|
2018-07-27
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2018 - 6/30/2018
|
|
2018-05-23
|
99
|
Miscellaneous
|
|
CHANGE OF PM - NESTE
|
|
2018-01-03
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2017 - 12/31/2017
|
|
2017-07-06
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2017 - 6/30/2017
|
|
2017-01-09
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2016 - 12/31/2016
|
|
2016-12-16
|
43
|
Site Activity Status Update Received
|
|
CONSULTANT TO PREPARE A CLOSURE REQUEST
|
|
2016-07-11
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2016 - 6/30/2016
|
|
2016-05-04
|
43
|
Site Activity Status Update Received
|
|
2015 ANNUAL SITE SUMMARY
|
|
2016-01-06
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2015 - 12/31/2015
|
|
2015-07-13
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2015 - 6/30/2015
|
|
2015-05-20
|
99
|
Miscellaneous
|
|
SUBMIT SITE FOR CLOSURE REVIEW
|
|
2015-03-20
|
99
|
Miscellaneous
|
|
ALTERNATE LOCATION FOR GROUNDWATER MONITORING WELL ACCEPTABLE
|
|
2015-03-19
|
43
|
Site Activity Status Update Received
|
|
REQUEST FOR ALTERNATE GROUNDWATER MONITORING WELL LOCATION
|
|
2015-03-03
|
38
|
Site Investigation Report (SIR) Approved
|
|
INSTALL ADDT'L GW MONITORING WELLS & COLLECT SOIL SAMPLES AT INSTALLATION. IMPLEMENT MONITORING PRGM
|
|
2015-01-08
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2014 - 12/31/2014
|
|
2014-10-16
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
SUMMARY OF ADDT'L SI ACTIVITIES
|
|
2014-08-25
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2014 - 6/30/2014
|
|
2014-04-23
|
140
|
Site Investigation Report (SIR) Not Approved
|
|
DEGREE AND EXTENT OF SOIL AND GROUNDWATER IMPACTS NOT DEFINED
|
|
2014-03-11
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
|
|
2013-09-26
|
43
|
Site Activity Status Update Received
|
|
CONSULTANT IS IN THE PROCESS OF PREPARING A REPORT FOR TYCO REVIEW
|
|
2013-04-10
|
43
|
Site Activity Status Update Received
|
|
SITE INVESTIGATION INITIATED BUT NOT COMPLETE
|
|
2012-10-23
|
30
|
Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
|
|
PROCEED WITH CHANGES TO SOIL AND GROUNDWATER SAMPLE PARAMETERS
|
|
2012-10-22
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
|
|
2012-08-20
|
2
|
Responsible Party (RP) letter sent
|
|
|
|
2012-06-14
|
1
|
Notification of Hazardous Substance Discharge
|
|
UNDERGROUND CABLE INSTALLATION 06/14/212
|