02-60-529589
SHEBOYGAN RIVER & HARBOR (SF NPL)
|
Activity Type / Status | Jurisdiction |
---|---|
ERP / OPEN | DNR RR |
Location Name | County | DNR Region |
---|---|---|
SHEBOYGAN RIVER & HARBOR | SHEBOYGAN | SOUTHEAST |
Address | Municipality |
---|---|
2025 MARYLAND AVE | SHEBOYGAN |
PLSS Description | Latitude (WGS84) | Longitude (WGS84) | Google Maps | RR Sites Map |
---|---|---|---|---|
SW 1/4 of the NW 1/4 of Sec 27, T15N, R23E | 43.7422423 | -87.7396452 |
Additional Activity Details | Acres |
---|---|
UNKNOWN |
Facility ID | PECFA No. | EPA ID | Start Date | End Date |
---|---|---|---|---|
460143200 | WID980996367 | 1991-01-01 |
Above Ground Petrol Tank |
Drycleaner |
EPA NPL Site |
EPA Superfund |
PECFA Funds Eligible |
PFAS |
ROW Impact |
Sediments |
Underground Petrol Tank |
WI DOT Site |
---|---|---|---|---|---|---|---|---|---|
Date | Code | Name | File | Comment | |
---|---|---|---|---|---|
2023-12-15 | 99 | Miscellaneous | FOLLOW-UP ON 12/11/23 DNR & EPA MEETING | ||
2023-12-12 | - | Site Assessment | |||
2023-12-12 | - | Site Assessment | |||
2023-11-14 | 43 | Site Activity Status Update Received | EPA COMMENTS ON 2022 FISH MONITORING REPORT | ||
2023-11-14 | 43 | Site Activity Status Update Received | EPA COMMENTS ON 2022 SEDIMENT MONITORING REPORT | ||
2023-10-02 | 43 | Site Activity Status Update Received | EPA APPROVE TIMELINE EXTENSION FOR SAMPLING & ANALYSIS PLAN | ||
2023-07-31 | 99 | Miscellaneous | DNR COMMENTS TO EPA ON SERIAL LETTER #86 | ||
2023-07-14 | 43 | Site Activity Status Update Received | SERIAL LETTER 86; SME RESPONSE TO EPA REQUEST ADDITIONAL DELINEATION | ||
2023-05-08 | 43 | Site Activity Status Update Received | EPA REQUEST ADDITIONAL DELINEATION ON FORMER TECUMSEH PROPERTY | ||
2023-01-17 | 43 | Site Activity Status Update Received | 2022 FISH MONITORING REPORT | ||
2023-01-16 | 43 | Site Activity Status Update Received | 2022 SURFACE SEDIMENT MONITORING REPORT | ||
2022-12-07 | 43 | Site Activity Status Update Received | 2022 INSPECTION REPORT | ||
2022-11-14 | 43 | Site Activity Status Update Received | SERIAL LETTER 66; GROUNDWATER MONITORING REPORT | ||
2022-09-30 | - | Maps | MAPS | ||
2022-07-28 | - | Site Investigation | |||
2022-06-29 | 99 | Miscellaneous | SME RESPONSE COMMENTS TO EPA COMMENTS DATED 06/24/2022 | ||
2022-06-24 | 99 | Miscellaneous | EPA RESPONSE COMMENTS ON REVISED STEP-BORING LOCATIONS | ||
2022-04-22 | 99 | Miscellaneous | EPA COMMENTS ON PROPOSED STEP-OUT BORING LOCATIONS FOR EE/CA INVESTIGATION | ||
2022-04-13 | 99 | Miscellaneous | DNR COMMENTS TO EPA ON PRELIMINARY REMEDIATION GOAL FOR RECREATIONAL SOIL | ||
2022-03-29 | 99 | Miscellaneous | EVALUATION OF PRELIMINARY REMEDIATION GOAL FOR RESIDENTIAL SOILS | ||
2021-09-09 | 43 | Site Activity Status Update Received | SERIAL LETTER 73; GROUNDWATER MONITORING REPORT | ||
2021-07-21 | 314 | Superfund Decision Document (ROD or ESD) - See Description | EXPLANATION OF SIGNIFICANT DIFFERENCES | ||
2021-06-15 | 99 | Miscellaneous | MAY 3, 2021 SAMPLING PLAN | ||
2021-04-07 | 99 | Miscellaneous | RESOLUTION OF OUTSTANDING ISSUES | ||
2021-04-06 | 99 | Miscellaneous | ENGINEERING EVALUATION & COST ANALYSIS MEMO FROM EPA | ||
2021-01-11 | 99 | Miscellaneous | EPA RESPONSE TO SERIAL LETTER 67 | ||
2020-08-21 | 326 | Superfund Five Year Review Report Signed | THIRD FIVE YEAR REVIEW SIGNED | ||
2020-08-06 | 99 | Miscellaneous | EPA & DNR REVIEW COMMENTS ON SAMPLING ANALYSIS PLAN | ||
2020-07-22 | 43 | Site Activity Status Update Received | SERIAL LETTER 64; 2020 GROUNDWATER MONITORING REPORT | ||
2020-07-13 | 99 | Miscellaneous | DNR COMMENTS TO EPA ON SITE INVESTIGATION | ||
2020-05-29 | 99 | Miscellaneous | SHEBOYGAN FALLS SAMPLING PLAN | ||
2020-04-23 | 99 | Miscellaneous | SME RESPONSE TO SERIAL LETTER 61 | ||
2020-04-23 | 43 | Site Activity Status Update Received | SERIAL LETTER 62; DATA GAP ANALYSIS REPORT | ||
2020-04-02 | 99 | Miscellaneous | SAMPLING ANALYSIS PLAN QUESTIONS | ||
2020-03-25 | 99 | Miscellaneous | EPA REVIEW COMMENTS ON REMEDIAL ACTION PLAN | ||
2019-07-11 | 43 | Site Activity Status Update Received | 2019 GROUNDWATER MONITORING REPORT | ||
2019-07-09 | 99 | Miscellaneous | FLOODPLAIN WORM SAMPLING RPT - 2019 | ||
2018-12-17 | 29 | Phase II Environmental Site Assessment (ESA) Rpt Received | DOT PHASE 2.5 & CONCURRENCE TO CREATE A NAR - #09-60-582891 | ||
2018-11-08 | 147 | Remedial Action (RA) Design Report Received (non-fee) | |||
2018-09-14 | 29 | Phase II Environmental Site Assessment (ESA) Rpt Received | SUPPLEMENTAL PHASE II ESA | ||
2018-06-11 | - | Website URL | Sheboygan Harbor & River EPA Superfund NPL/SAA Website This EPA website contains additional information about this Activity. | ||
2017-11-21 | 43 | Site Activity Status Update Received | 2017 SEDIMENT MONITORING REPORT | ||
2017-09-28 | 43 | Site Activity Status Update Received | 2017 GROUNDWATER MONITORING REPORT | ||
2017-08-11 | 29 | Phase II Environmental Site Assessment (ESA) Rpt Received | SHEBOYGAN RIVER AND HARBOR SUPERFUND SITE TECUMSEH DEWATERING SITE | ||
2017-08-10 | 147 | Remedial Action (RA) Design Report Received (non-fee) | REMEDIAL ACTION PLAN SHEBOYGAN RIVER AND HARBOR SUPERFUND SITE TECUMSEH DEWATERING SITE | ||
2016-11-09 | 99 | Miscellaneous | SAMPLING HAS STARTED FOR ULTIMATE CLOSING OF DE-WATERING SITES | ||
2016-05-17 | 43 | Site Activity Status Update Received | SERIAL LETTER 29; SAMPLING ANALYSIS PLAN | ||
2015-12-09 | 99 | Miscellaneous | DNR & EPA WORKING WITH RP TO CLOSE OUT SEDIMENT DE-WATERING SITES. | ||
2015-05-20 | 99 | Miscellaneous | APPROVED WORK PLAN | ||
2015-04-17 | 99 | Miscellaneous | 2014 ANNUAL FISH MONITORING REPORT | ||
2015-04-14 | 99 | Miscellaneous | 2013 FISH MONITORING RPT | ||
2015-02-09 | 99 | Miscellaneous | FINAL REMEDIATION COMPLETE FINAL APPROVAL PENDING | ||
2014-08-28 | 326 | Superfund Five Year Review Report Signed | SECOND FIVE YEAR REVIEW SIGNED | ||
2012-03-31 | 99 | Miscellaneous | ENVIRONMENTAL PROTECTION PLAN | ||
2012-02-28 | 99 | Miscellaneous | 2011 FISH MONITORING RPT | ||
2012-02-01 | 310 | Superfund Final Feasibility Study (FS) Submittal | FINAL FOCUSED FEASIBILITY STUDY | ||
2011-03-31 | 316 | Superfund Site Assessment DNR Planning Documentation | LOWER RIVER RAWP | ||
2011-02-28 | 99 | Miscellaneous | 2010 FISH MONITORING REPORT | ||
2010-12-15 | 314 | Superfund Decision Document (ROD or ESD) - See Description | EXPLANATION OF SIGNIFICANT DIFFERENCES | ||
2010-11-30 | 99 | Miscellaneous | UPPER RIVER 100% DESIGN | ||
2010-09-01 | 307 | Superfund Final Remedial Investigation (RI) Approval | REMEDIAL INVESTIGATION FOR FINAL FIELD SAMPLING PLAN | ||
2009-12-16 | 99 | Miscellaneous | EPA FLOODPLAIN SOIL EVALUATION MEMO | ||
2009-11-30 | 99 | Miscellaneous | LOWER RIVER PRE-DESIGN INVESTIGATION REPORT | ||
2009-09-30 | 99 | Miscellaneous | 2009 FISH MONITORING RPT | ||
2009-09-01 | 326 | Superfund Five Year Review Report Signed | FIRST FIVE YEAR REVIEW SIGNED | ||
2009-06-30 | 99 | Miscellaneous | BASELINE UPPER AND LOWER RIVER FISH MONITORING RPT | ||
2009-06-30 | 99 | Miscellaneous | QUALITY ASSURANCE PROJECT PLAN | ||
2009-06-30 | 316 | Superfund Site Assessment DNR Planning Documentation | LOWER RIVER REMEDIAL DESIGN WORK PLAN | ||
2009-06-30 | 316 | Superfund Site Assessment DNR Planning Documentation | LOWER RIVER REMEDIAL DESIGN WORK PLAN | ||
2008-08-13 | 99 | Miscellaneous | POST REMEDIATION MONITORING PLAN | ||
2008-02-28 | 99 | Miscellaneous | 2007 CONSTRUCTION DOCUMENTATION REPORT | ||
2006-10-30 | 316 | Superfund Site Assessment DNR Planning Documentation | REMEDIAL ACTION WORK PLAN UPPER RIVER | ||
2006-03-01 | 29 | Phase II Environmental Site Assessment (ESA) Rpt Received | PHASE II UPPER RIVER SEDIMENT REMOVAL DESIGN | ||
2006-01-09 | 305 | Superfund Enforcement Documents - See Description | AMENDED CONSENT DECREE FOR UPPER RIVER | ||
2005-11-30 | 29 | Phase II Environmental Site Assessment (ESA) Rpt Received | PRE-DESIGN INVESTIGATION RESULTS PHASE II | ||
2005-09-30 | 28 | Phase I Environmental Site Assessment (ESA) Rpt Received | PHASE I COMPLETION REPORT | ||
2005-06-23 | 99 | Miscellaneous | EVALUATION OF FLOODPLAIN AREA 6 COMMENTS | ||
2005-04-30 | 29 | Phase II Environmental Site Assessment (ESA) Rpt Received | SEDIMENT PRE-DESIGN INVESTIGATION RESULTS PHASE II | ||
2005-04-30 | 29 | Phase II Environmental Site Assessment (ESA) Rpt Received | FLOODPLAIN PRE-DESIGN INVESTIGATION RESULTS PHASE II | ||
2005-04-02 | 99 | Miscellaneous | SEDIMENT DEPOSIT PCB CHEMICAL DATA REPORTS VOLUME I | ||
2005-04-02 | 99 | Miscellaneous | SEDIMENT DEPOSIT PCB CHEMICAL DATA REPORTS VOLUME II | ||
2005-04-02 | 99 | Miscellaneous | FLOODPLAINS CHEMICAL DATA REPORT | ||
2004-05-31 | 99 | Miscellaneous | FIELD SAMPLING PLAN UPPER RIVER PHASE I & II | ||
2004-05-01 | 43 | Site Activity Status Update Received | PHASE 1 PROJECT SPECIFICATIONS VOLUME 4 | ||
2004-02-20 | 99 | Miscellaneous | REMEDIAL DESIGN 100% FINAL | ||
2003-12-30 | 99 | Miscellaneous | WATER MANAGEMENT PLAN FOR CONSTRUCTION ACTIVITIES UPPER RIVER PHASE I | ||
2003-04-01 | 99 | Miscellaneous | 2022 INTERIM MONITORING REPORT | ||
2002-07-19 | 99 | Miscellaneous | 2001 INTERIM MONITORING REPORT | ||
2001-11-06 | 99 | Miscellaneous | FINAL REPORT ON CLEANUP WORK ACTIVITIES | ||
2001-11-02 | 305 | Superfund Enforcement Documents - See Description | PARTIAL RD/RA CONSENT DECREE | ||
2001-09-05 | 99 | Miscellaneous | 2000 INTERIM MONITORING REPORT | ||
2001-03-30 | 305 | Superfund Enforcement Documents - See Description | PARTIAL CONSENT DECREE | ||
2001-03-30 | 314 | Superfund Decision Document (ROD or ESD) - See Description | RECORD OF DECISION REMEDY SELECTION | ||
2001-03-30 | 316 | Superfund Site Assessment DNR Planning Documentation | SCOPE OF WORK FOR RD/RA | ||
2001-02-28 | 99 | Miscellaneous | REVISED COMMUNITY INVOLVEMENT PLAN | ||
2001-02-09 | 99 | Miscellaneous | PHASE I DATA COLLECTION MODEL SELECTION | ||
2001-01-19 | 99 | Miscellaneous | MASS BALANCE APPROACH FOR ASSESSING PCB MOVEMENT | ||
2000-10-12 | 99 | Miscellaneous | SPECIES TISSUE REPORTS | ||
2000-07-30 | 99 | Miscellaneous | CORRESPONDENCE REGARDING REMEDY ACCEPTANCE | ||
2000-06-13 | 305 | Superfund Enforcement Documents - See Description | CONSENT DECREE NEGOTIATIONS | ||
2000-05-12 | 314 | Superfund Decision Document (ROD or ESD) - See Description | RECORD OF DECISION | ||
2000-04-01 | 316 | Superfund Site Assessment DNR Planning Documentation | FINAL FOOD CHAIN & SEDIMENT CONTAMINANT ASSESSMENT | ||
2000-04-01 | 316 | Superfund Site Assessment DNR Planning Documentation | FINAL PROJECT REPORT FOR EPA | ||
2000-03-14 | 305 | Superfund Enforcement Documents - See Description | ADMINISTRATIVE ORDER | ||
2000-02-28 | 99 | Miscellaneous | SAMPLING WORK PLAN ADDENDUM | ||
2000-02-07 | 99 | Miscellaneous | 1999 ANNUAL INTERIM MONITORING REPORT | ||
1999-11-30 | 99 | Miscellaneous | TECHNICAL MEMO EXT SOURCE ASSESSMENT | ||
1999-11-15 | 99 | Miscellaneous | FLOODPLAIN TERRESTRIAL ECOLOGICAL RISK ASSESSMENT | ||
1999-07-30 | 99 | Miscellaneous | CORRESPONDENCE REGARDING REMEDY ACCEPTANCE | ||
1999-05-27 | 311 | Superfund Proposed Plan (PP) Issued | PROPOSED PLAN | ||
1999-03-15 | 99 | Miscellaneous | NATIONAL REMEDY SELECTION BRIEFING PACKAGE | ||
1999-01-11 | 99 | Miscellaneous | FEASIBILITY APPROVED BY EPA | ||
1998-12-10 | 92 | Operation & Maintenance (O&M) Report Received (non-fee) | O & M ACTIVITIES | ||
1998-11-30 | 99 | Miscellaneous | AQUATIC ECOLOGICAL RISK ASSESSMENT VOLUMES I THROUGH III | ||
1998-05-31 | 99 | Miscellaneous | FISH CONSUMPTION EXPOSURE ASSESSMENT STUDY | ||
1998-04-30 | 310 | Superfund Final Feasibility Study (FS) Submittal | FEASIBILITY STUDY VOL I & II | ||
1998-04-21 | 316 | Superfund Site Assessment DNR Planning Documentation | GW SAMPLING WORK PLAN | ||
1998-03-18 | 310 | Superfund Final Feasibility Study (FS) Submittal | FEASIBILITY APPROVAL | ||
1997-09-30 | 99 | Miscellaneous | FEASIBILITY STUDY REPORT VOLUMES I+II | ||
1997-08-18 | 99 | Miscellaneous | ARARS DOCUMENTS | ||
1997-08-08 | 99 | Miscellaneous | FINAL AQUATIC ECOLOGICAL ASSESSMENT WORK PLAN | ||
1997-07-14 | 99 | Miscellaneous | ARAR | ||
1997-05-19 | 99 | Miscellaneous | ECOLOGICAL RISK ASSESSMENT PROBLEM FORMULATION | ||
1997-05-06 | 99 | Miscellaneous | PRELIMINARY COST ESTIMATES FOR REMEMDIAL ACTIONS | ||
1997-03-13 | 99 | Miscellaneous | PROJECT HISTORY TIMELINE | ||
1996-12-31 | 316 | Superfund Site Assessment DNR Planning Documentation | WORK PLAN/QAPP INTERIM MONITORING PROGRAM | ||
1996-11-30 | 99 | Miscellaneous | SEDIMENT TRANSPORT STUDY | ||
1996-08-29 | 99 | Miscellaneous | WHITE SUCKER FISH STUDY | ||
1996-05-31 | 99 | Miscellaneous | DRAFT FEASIBILITY STUDY PROCESS | ||
1996-04-03 | 99 | Miscellaneous | EPA CURRENT POSITION CORRESPONDENCE, FOIA EXEMPT | ||
1996-02-28 | 99 | Miscellaneous | ENDANGERED RESOURCES INFORMATION REVIEW | ||
1995-10-30 | 307 | Superfund Final Remedial Investigation (RI) Approval | ALTERNATIVE SPECIFIC RI REPORT | ||
1995-10-01 | 147 | Remedial Action (RA) Design Report Received (non-fee) | REMEDIAL ACTION PLAN | ||
1995-09-01 | 316 | Superfund Site Assessment DNR Planning Documentation | FIELD PROCEDURES PLAN | ||
1995-01-24 | 99 | Miscellaneous | DISPOSAL APPROVAL OF PCB CONTAMINATED SEDIMENT | ||
1994-03-07 | 99 | Miscellaneous | PUBLIC REVIEW RAP | ||
1992-09-01 | 316 | Superfund Site Assessment DNR Planning Documentation | BIODEGRADATION PILOT STUDY WORKPLAN | ||
1992-07-16 | 316 | Superfund Site Assessment DNR Planning Documentation | ALTERNATE ARRAY DOCUMENT | ||
1992-07-10 | 99 | Miscellaneous | WATER QUALITY SEDIMENT CRITERIA MEMO | ||
1992-06-19 | 356 | Superfund Removal Action Taken | REMOVAL ACTION CONSTRUCTION DOCUMENTATION REPORT | ||
1992-04-24 | 99 | Miscellaneous | SOLVENT EXTRACTION BENCH-SCALE STUDY | ||
1992-03-01 | 99 | Miscellaneous | DRAFT REMEDIAL INV. REPT VOL 1, 2, 3, 4 | ||
1992-03-01 | 99 | Miscellaneous | REMOVAL ACTION (CONSTRUCTION DOC. REPT VOL 1 & 2 | ||
1992-02-28 | 99 | Miscellaneous | BIODEGRADATION PILOT STUDY PROJECT UPDATE | ||
1992-02-21 | 92 | Operation & Maintenance (O&M) Report Received (non-fee) | O & M ACTIVITIES | ||
1992-01-15 | 99 | Miscellaneous | EPA MEETING SUMMARY | ||
1991-09-13 | 305 | Superfund Enforcement Documents - See Description | COMPLIANCE ORDER | ||
1991-05-24 | 316 | Superfund Site Assessment DNR Planning Documentation | REMOVAL ACTION WORK PLAN COMMENTS | ||
1991-05-14 | 316 | Superfund Site Assessment DNR Planning Documentation | QUALITY ASSURANCE PROGRAM FOR LEAK DETECTION | ||
1991-03-31 | 99 | Miscellaneous | INFORMATION SUMMARY, AREA OF CONCERN | ||
1991-01-31 | 99 | Miscellaneous | PCB IN SHEBOYGAN RIVER STUDY | ||
1991-01-31 | 99 | Miscellaneous | CONSTRUCTION DOCUMENTATION REPORT | ||
1991-01-01 | 1 | Notification of Hazardous Substance Discharge | Added during data cleanup | ||
1990-12-17 | 99 | Miscellaneous | ALTERNATIVE ARRAY DRAFT DOCUMENT | ||
1990-12-17 | 399 | Superfund Remedial Draft Document | ALTERNATIVE ARRAY DRAFT DOCUMENT | ||
1990-11-10 | 99 | Miscellaneous | COMMENTS ON SEDIMENT CAPSULE CORRESPONDENCE | ||
1990-10-31 | 316 | Superfund Site Assessment DNR Planning Documentation | WORK PLAN/QAPP/HSCP | ||
1990-10-12 | 99 | Miscellaneous | PROJECT UPDATE CORRESPONDENCE | ||
1990-10-03 | 92 | Operation & Maintenance (O&M) Report Received (non-fee) | O & M ACTIVITIES | ||
1990-09-30 | 99 | Miscellaneous | EPA FACT SHEET | ||
1990-08-22 | 99 | Miscellaneous | ALTERNATIVE SPECIFIC REMEDIAL INVESTIGATION QAPP APPROVED | ||
1990-07-02 | 316 | Superfund Site Assessment DNR Planning Documentation | FINAL SAMPLING PLAN | ||
1990-07-01 | 316 | Superfund Site Assessment DNR Planning Documentation | SAMPLING WORKPLAN | ||
1990-01-30 | 99 | Miscellaneous | SHEBOYGAN REMEDIAL ACTION PLAN BACTERIOLOGICAL SURVEY | ||
1989-10-01 | 316 | Superfund Site Assessment DNR Planning Documentation | HEALTH, SAFETY, AND CONTINGENCY PLAN | ||
1989-07-01 | 147 | Remedial Action (RA) Design Report Received (non-fee) | REMEDIAL ACTION PLAN | ||
1989-03-31 | 99 | Miscellaneous | PCB LEVELS IN HUMAN FLUIDS STUDY | ||
1989-01-31 | 305 | Superfund Enforcement Documents - See Description | EPA ADMIN ORDER | ||
1988-09-30 | 351 | Superfund Site Assessment Site Inspection (SI) | SITE INVESTIGATION REPORT | ||
1988-02-18 | 99 | Miscellaneous | STATUS UPDATE CORRESPONDENCE | ||
1987-04-30 | 316 | Superfund Site Assessment DNR Planning Documentation | QUALITY ASSURANCE PROJECT PLAN | ||
1986-12-08 | 99 | Miscellaneous | FINAL COMMUNITY RELATIONS PLAN | ||
1986-08-11 | 14 | Notice of Violation (NOV) Issued | DNR ENFORCEMENT REPORT OF VIOLATION TO TECUMSEH | ||
1986-07-31 | 99 | Miscellaneous | FINAL QUALITY ASSURANCE PROJECT PLAN | ||
1986-07-30 | 316 | Superfund Site Assessment DNR Planning Documentation | HEALTH AND SAFETY PLAN | ||
1986-05-01 | 301 | Superfund NPL, NPL Proposed or Alternative Approach Site | CONSTRUCTION DOC REPORT | ||
1986-04-18 | 305 | Superfund Enforcement Documents - See Description | ADMINISTRATIVE ORDER OF CONSENT | ||
1986-04-03 | 99 | Miscellaneous | SIR REVISIONS JANUARY 1986 AND MARCH 1986 | ||
1986-01-10 | 316 | Superfund Site Assessment DNR Planning Documentation | ADDENDUM TO PRP WORK PLAN | ||
1985-11-15 | 351 | Superfund Site Assessment Site Inspection (SI) | REMEDIAL INVESIGATION/FEASIBILITY STUDY | ||
1985-10-21 | 316 | Superfund Site Assessment DNR Planning Documentation | WORK PLAN REMEDIAL INVESTIGATION/FEASIBILITY STUDY | ||
1985-05-24 | 315 | Superfund Site Assessment Transmittal Memos | EPA CONFIDENTIAL CORRESPONDENCE | ||
1985-05-22 | 319 | Superfund Site Assessment HRS Scoring Package | COMMENTS ON EPA HRS SCORING | ||
1985-05-15 | 99 | Miscellaneous | MAINTENANCE DREDGING OF UNCONTAMINATED SEDIMENTS | ||
1985-05-15 | 99 | Miscellaneous | EPA CORRESPONDENCE | ||
1985-02-22 | 99 | Miscellaneous | WORKPLAN MEMORANDUM FOR SHEBOYGAN RIVER | ||
1985-01-16 | 319 | Superfund Site Assessment HRS Scoring Package | EPA SCORING DOCUMENT | ||
1982-11-29 | 305 | Superfund Enforcement Documents - See Description | CONSENT AGREEMENT | ||
1982-09-24 | 305 | Superfund Enforcement Documents - See Description | STATEMENT WITH REGARD TO SETTLEMENT | ||
1982-07-30 | 99 | Miscellaneous | DISCUSSION WITH DNR & EPA ON INSPECTION OF SHEBOYGAN FALLS LANDFILL | ||
1982-04-23 | 43 | Site Activity Status Update Received | SAMPLING FOR TSCA COMPLAINT | ||
1982-03-18 | 99 | Miscellaneous | COMPLAINT AND NOTICE OF OPPORTUNITY | ||
1982-01-22 | 99 | Miscellaneous | EPA DREDGING CORRESPONDENCE | ||
1981-10-14 | 99 | Miscellaneous | RESPONSE TO EPA COMMENTS | ||
1981-09-28 | 99 | Miscellaneous | DISCUSSION ON DNR AND EPA PERMITS | ||
1981-08-14 | 92 | Operation & Maintenance (O&M) Report Received (non-fee) | OPERATIONS MANUAL AND DESIGN REPORT FOR A CHEMICAL WASTE LANDFILL- PCB DISPOSAL | ||
1981-07-21 | 99 | Miscellaneous | LANDFILL PRELIMINARY SPECIFICATION & COST ANALYSIS | ||
1981-06-26 | 99 | Miscellaneous | DREDGING OPTIONS CORRESPONDENCE | ||
1980-06-25 | 99 | Miscellaneous | GUIDELINES FOR HANDLING PCB CONTAMINATED DREDGE SOILS CORRESPONDENCE | ||
1980-01-31 | 99 | Miscellaneous | PCB CONTENT IN SHEBOYGAN RIVER SEDIMENTS | ||
1979-10-03 | 99 | Miscellaneous | PROPOSED PCB SAMPLING PLAN FOR SHEBOYGAN HARBOR AND RIVER BOTTOM SEDIMENT | ||
1979-02-22 | 99 | Miscellaneous | PCB INVESTIGAIONS CASE STUDY PRESENTATION | ||
1978-09-11 | 99 | Miscellaneous | SUMMARY OF 8/10/78 SITE INSPECTION | ||
1978-08-25 | 99 | Miscellaneous | DISCUSSION ON CITYS SEWER CONSTRUCTION PROJECT | ||
1978-08-02 | 43 | Site Activity Status Update Received | CITY ACCESS PERMISSION | ||
1978-07-31 | 305 | Superfund Enforcement Documents - See Description | ADMINISTRATIVE ORDER | ||
1978-07-18 | 99 | Miscellaneous | DNR INSPECTION OF TECUMSEH PROPERTY | ||
1978-07-12 | 99 | Miscellaneous | FINAL REPORT ON THE INVESTIGATION OF PCBS IN THE SHEBOYGAN RIVER SYSTEM | ||
1978-06-10 | 99 | Miscellaneous | PCB FINAL REPORT CORRESPONDENCE ON POSSIBLE APPROVAL | ||
1978-05-24 | 99 | Miscellaneous | SUMMARY OF EVENTS THUS FAR | ||
1978-05-22 | 99 | Miscellaneous | RESPONSE TO DNR ORDER | ||
1978-05-12 | 305 | Superfund Enforcement Documents - See Description | ADMINISTRATIVE SPECIAL ORDER | ||
1978-05-12 | 99 | Miscellaneous | FINDINGS OF FACT | ||
1978-05-12 | 99 | Miscellaneous | SAMPLING AT THE TECUMSEH PROPERTY | ||
1978-05-08 | 99 | Miscellaneous | WATER QUALITY PROGRAM DESIGN | ||
1974-10-02 | 99 | Miscellaneous | REPORT ON THE DEGREE OF POLLUTIONIN BOTTOM SEDIMENTS | ||
1963-04-17 | 99 | Miscellaneous | REPORT ON THE DEGREE OF POLLUTIONIN BOTTOM SEDIMENTS |
GWEN SALIARES gwen.saliares@wisconsin.gov |