|
2024-05-13
|
43
|
Site Activity Status Update Received
|
|
STATUS UPDATE
|
|
2024-04-12
|
43
|
Site Activity Status Update Received
|
|
MARCH 2024 MONTHLY PROGRESS REPORT
|
|
2024-03-13
|
43
|
Site Activity Status Update Received
|
|
FEBRUARY 2024 MONTHLY PROGRESS REPORT
|
|
2024-02-20
|
43
|
Site Activity Status Update Received
|
|
JANUARY 2024 MONTHLY PROGRESS REPORT
CAMPMARINA FORMER MANUFACTURED GAS PLANT
|
|
2024-01-30
|
99
|
Miscellaneous
|
|
THIRD PARTY NOTIFICATION
|
|
2024-01-16
|
43
|
Site Activity Status Update Received
|
|
STATUS UPDATE REPORT
|
|
2023-12-12
|
43
|
Site Activity Status Update Received
|
|
NOVEMBER 2023 MONTHLY PROGRESS REPORT
|
|
2023-11-21
|
43
|
Site Activity Status Update Received
|
|
OCTOBER 2023 MONTHLY PROGRESS REPORT
|
|
2023-10-18
|
43
|
Site Activity Status Update Received
|
|
SEPTEMBER 2023 MONTHLY PROGRESS REPORT
|
|
2023-09-12
|
43
|
Site Activity Status Update Received
|
|
AUGUST 2023 MONTHLY PROGRESS REPORT
|
|
2023-09-11
|
99
|
Miscellaneous
|
|
VPLE AND CASE CLOSURE REVIEW COMMENTS
|
|
2023-08-23
|
43
|
Site Activity Status Update Received
|
|
JULY MONTHLY
|
|
2023-08-08
|
99
|
Miscellaneous
|
|
THIRD PARTY NOTIFICATION
|
|
2023-07-14
|
43
|
Site Activity Status Update Received
|
|
JUNE 2023 MONTHLY REPORT
|
|
2023-06-15
|
43
|
Site Activity Status Update Received
|
|
MAY 2023 MONTHLY PROGRESS REPORT
|
|
2023-05-19
|
43
|
Site Activity Status Update Received
|
|
APRIL 2023 MONTHLY PROGRESS REPORT
|
|
2023-05-15
|
99
|
Miscellaneous
|
|
NEW EPA RPM (PROJECT MANAGER)
|
|
2023-04-21
|
43
|
Site Activity Status Update Received
|
|
MARCH 2023 PROGRESS RPT
|
|
2023-04-04
|
326
|
Superfund Five Year Review Report Signed
|
|
FIVE YEAR REPORT #2 FOR THE UPLAND OU
|
|
2023-03-22
|
43
|
Site Activity Status Update Received
|
|
FEBRUARY 2023 MONTHLY PROGRESS REPORT
|
|
2023-02-16
|
43
|
Site Activity Status Update Received
|
|
JANUARY 2023 MONTHLY PROGRESS REPORT
|
|
2023-01-18
|
43
|
Site Activity Status Update Received
|
|
DECEMBER 2022 MONTHLY PROGRESS REPORT
|
|
2023-01-18
|
99
|
Miscellaneous
|
|
THIRD PARTY NOTIFICATION
|
|
2022-12-13
|
43
|
Site Activity Status Update Received
|
|
DECEMBER MONTHLY PROGRESS RPT
|
|
2022-11-21
|
43
|
Site Activity Status Update Received
|
|
MONTHLY REPOTY - OCTOBER 2022
|
|
2022-10-17
|
43
|
Site Activity Status Update Received
|
|
MONTHLY REPORT, SPETEMBER 2022
|
|
2022-09-19
|
99
|
Miscellaneous
|
|
AUGUST MONTHLY PROGRESS REPORT, NO GROUNDWATER TABLES INCLUDED
|
|
2022-08-15
|
43
|
Site Activity Status Update Received
|
|
JULY MONTHLY REPORT
|
|
2022-07-21
|
43
|
Site Activity Status Update Received
|
|
JUNE 2022 MONTHLY PROGRESS RPT
|
|
2022-06-29
|
99
|
Miscellaneous
|
|
THIRD PARTY NOTIFICATION
|
|
2022-06-21
|
43
|
Site Activity Status Update Received
|
|
MAY STATUS REPORT
|
|
2022-05-16
|
43
|
Site Activity Status Update Received
|
|
STATUS UPDATE APRIL 2022 MONTHLY PROGRESS REPORT
|
|
2022-04-18
|
43
|
Site Activity Status Update Received
|
|
MARCH 2022 MONTHLY PROGRESS REPORT
|
|
2022-03-14
|
43
|
Site Activity Status Update Received
|
|
FEBRUARY 2022 MONTHLY PROGRESS REPORT
|
|
2022-02-21
|
43
|
Site Activity Status Update Received
|
|
JAN 2022 MONTHLY PROGRESS REPORT
|
|
2022-01-19
|
43
|
Site Activity Status Update Received
|
|
DECEMBER 2021 MONTHLY PROGRESS RPT
|
|
2022-01-13
|
99
|
Miscellaneous
|
|
RECENT SAMPLING RESULTS
|
|
2021-12-15
|
43
|
Site Activity Status Update Received
|
|
NOVEMBER 2021 MONTHLY PROGRESS RPT
|
|
2021-11-18
|
43
|
Site Activity Status Update Received
|
|
OCTOBER 2021 MONTHLY PROGRESS RPT
|
|
2021-10-29
|
99
|
Miscellaneous
|
|
EPA NOTIFICATION TO DNR OF EPA INTENTION TO CONDUCT A FIVE YEAR REVIEW
|
|
2021-10-20
|
43
|
Site Activity Status Update Received
|
|
MONTHLY PROGRESS RPT - SEPTEMBER 2021
|
|
2021-09-20
|
43
|
Site Activity Status Update Received
|
|
AUGUST 2021 PROGRESS RPT
|
|
2021-08-16
|
43
|
Site Activity Status Update Received
|
|
JULY 2021 MONTHLY PROGRESS RPT
|
|
2021-07-26
|
43
|
Site Activity Status Update Received
|
|
JUNE 2021 PROGRESS RPT
|
|
2021-07-20
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER SAMPLE RESULTS
|
|
2021-07-16
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER DATA
|
|
2021-07-12
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER SAMPLE RESULTS
|
|
2021-04-06
|
130
|
DNR Regulatory Reminder Sent
|
|
VAPOR INTRUSION AND TCE REMINDER LETTER
|
|
2021-03-01
|
99
|
Miscellaneous
|
|
NEW EPA (RPM)
|
|
2021-01-28
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER SAMPLE RESULTS
|
|
2021-01-22
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER SAMPLE RESULTS
|
|
2020-08-17
|
130
|
DNR Regulatory Reminder Sent
|
|
EMERGING CONTAMINANTS REMINDER LETTER
|
|
2020-07-24
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER SAMPLE RESULTS
|
|
2020-05-15
|
-
|
Site Investigation
|
|
|
|
2020-05-15
|
-
|
Site Investigation
|
|
|
|
2020-05-08
|
-
|
Site Investigation
|
|
|
|
2020-05-08
|
-
|
Site Investigation
|
|
|
|
2020-05-07
|
-
|
Site Investigation
|
|
|
|
2020-05-07
|
-
|
Site Investigation
|
|
|
|
2020-05-07
|
-
|
Site Investigation
|
|
|
|
2020-05-06
|
-
|
Site Investigation
|
|
|
|
2020-05-06
|
-
|
Site Investigation
|
|
|
|
2020-01-29
|
99
|
Miscellaneous
|
|
DECEMBER 2019 GROUNDWATER SAMPLE RESULTS TABLE
|
|
2020-01-23
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER SAMPLE RESULTS
|
|
2019-09-11
|
99
|
Miscellaneous
|
|
OFFSITE SAMPLING RESULTS NOTIFICATION
|
|
2019-09-10
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER SAMPLE RESULTS
|
|
2019-08-22
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER MONITORING REPORT
|
|
2019-08-22
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER SAMPLE RESULTS
|
|
2019-07-24
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2019 - 6/30/2019
|
|
2019-04-02
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER SAMPLE RESULTS
|
|
2019-02-22
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER SAMPLE RESULTS
|
|
2019-01-29
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2018 - 12/31/2018
|
|
2018-10-22
|
43
|
Site Activity Status Update Received
|
|
MONTHLY PROGRESS REPORT
|
|
2018-09-26
|
99
|
Miscellaneous
|
|
EPA DEFERRAL TO STATE UPDATE
|
|
2018-09-14
|
326
|
Superfund Five Year Review Report Signed
|
|
FIVE-YEAR REPORT NUMBER 1
|
|
2018-09-06
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER MONITORING DATA NOTIFICATION
|
|
2018-09-04
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER SAMPLE RESULTS
|
|
2018-07-30
|
43
|
Site Activity Status Update Received
|
|
JUNE 2018 GROUNDWATER SAMPLING DATA
|
|
2018-07-27
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2018 - 6/30/2018
|
|
2018-07-25
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER SAMPLE RESULTS
|
|
2018-06-11
|
-
|
Website URL
|
|
WPSC Camp Marina MGP EPA Superfund NPL/SAA Website This EPA website contains additional information about this Activity.
|
|
2018-03-20
|
99
|
Miscellaneous
|
|
REC'D ADDENDUM NO.3, REVISION 1 TO THE MULTI-SITE QULITY ASSURANCE PROJECT PLAN 1
|
|
2018-02-28
|
43
|
Site Activity Status Update Received
|
|
REC'D JANUARY 2018 MONTHLY PROGRESS RPT
|
|
2018-02-26
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER SAMPLE RESULTS
|
|
2018-02-23
|
99
|
Miscellaneous
|
|
ADDENDUM NO. 3, REVISION 1 TO THE MULTI-SITE QUALITY ASSURANCE PROJECT PLAN 1
|
|
2018-01-15
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2017 - 12/31/2017
|
|
2018-01-02
|
43
|
Site Activity Status Update Received
|
|
MONTHLY STATUS REPORT, GROUNDWATER QUARTERLY SAMPLING DONE
|
|
2017-11-09
|
99
|
Miscellaneous
|
|
REC'D ADDENDUM 3 TO THE QUALITY ASSURANCE PLAN
|
|
2017-07-21
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER SAMPLE RESULTS
|
|
2017-07-17
|
43
|
Site Activity Status Update Received
|
|
5-YEAR REVIEW SEDIMENT SAMPLING UPDATE
|
|
2017-05-25
|
99
|
Miscellaneous
|
|
EPA 5 YEAR SAMPLING WORK PLAN APPROVAL
|
|
2017-02-27
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER SAMPLE RESULTS
|
|
2017-01-24
|
99
|
Miscellaneous
|
|
MONTHLY PROGRESS REPORT
|
|
2016-12-27
|
99
|
Miscellaneous
|
|
NOVEMBER 2016 PROGRESS REPORT
|
|
2016-12-27
|
99
|
Miscellaneous
|
|
NOTIFICATION OF 5-YEAR REVIEW FROM US EPA
|
|
2016-06-30
|
99
|
Miscellaneous
|
|
MONTHLY UPDATE
|
|
2016-06-07
|
99
|
Miscellaneous
|
|
MONTHLY PROGRESS REPORT
|
|
2016-03-29
|
99
|
Miscellaneous
|
|
MONTHLY PROGRESS REPORT
|
|
2016-01-04
|
99
|
Miscellaneous
|
|
ARAR MEMO
|
|
2015-12-09
|
99
|
Miscellaneous
|
|
EPA DEFERRAL TO STATE UPDATE
|
|
2015-11-15
|
99
|
Miscellaneous
|
|
5-YEAR REVIEW NOTIFICATION TO CITY OF SHEBOYGAN
|
|
2015-11-12
|
99
|
Miscellaneous
|
|
STATUS UPDATE
|
|
2015-11-06
|
99
|
Miscellaneous
|
|
5-YEAR REVIEW NOTIFICATION TO WPSC
|
|
2015-10-01
|
99
|
Miscellaneous
|
|
STATUS UPDATE
|
|
2015-08-31
|
99
|
Miscellaneous
|
|
STATUS UPDATE
|
|
2015-07-29
|
99
|
Miscellaneous
|
|
UPDATE
|
|
2015-07-21
|
99
|
Miscellaneous
|
|
STATUS UPDATE
|
|
2015-05-26
|
99
|
Miscellaneous
|
|
STATUS UPDATE
|
|
2015-03-24
|
99
|
Miscellaneous
|
|
STATUS UPDATE
|
|
2015-03-02
|
99
|
Miscellaneous
|
|
STATUS UPDATE
|
|
2014-07-17
|
99
|
Miscellaneous
|
|
REPORT FROM RP TO US EPA. "TECHNICAL IMPRACTICABILITY REPT"
|
|
2014-06-30
|
99
|
Miscellaneous
|
|
PROGRESS REPORT
|
|
2014-03-19
|
43
|
Site Activity Status Update Received
|
|
2013 ANNUAL GW MONITORING REPORT
|
|
2014-03-10
|
99
|
Miscellaneous
|
|
TECHNICAL IMPRACTICALITY REPT
|
|
2014-01-27
|
99
|
Miscellaneous
|
|
PROGRESS RPT
|
|
2013-10-31
|
151
|
Remedial Action (RA) Documentation Report Received (non-fee)
|
|
SEDIMENTS
|
|
2013-09-11
|
80
|
Closure Not Recommended
|
|
UPLAND PORTION WILL BE PLACED ON GIS PER RAD APPROVAL
|
|
2013-09-10
|
199
|
Additional Information Received (Fee-Based or Closure)
|
|
|
|
2013-08-22
|
198
|
Request for Additional Information (Fee-Based or Closure)
|
|
MORE INFO NEEDED
|
|
2013-08-01
|
151
|
Remedial Action (RA) Documentation Report Received (non-fee)
|
|
GLNPO DREDGING REPORT
|
|
2013-08-01
|
151
|
Remedial Action (RA) Documentation Report Received (non-fee)
|
|
GLNPO DREDGING REPORT APPENDIX Q5 - POST DREDGE SAMPLING ANALYTICALS
|
|
2013-07-25
|
99
|
Miscellaneous
|
|
DRAFT UPLAND OU ROD
|
|
2013-06-19
|
79
|
Case Closure Review Request Received
|
|
|
|
2013-06-06
|
149
|
Remedial Action (RA) Design Report Approved
|
|
APPROVAL FOR UPLAND PORTION - GIS REGISTRY
|
|
2013-06-06
|
220
|
Continuing Obligation - Soil at Industrial Levels
|
|
|
|
2013-06-06
|
222
|
Continuing Obligation - Maintain Cap Over Contaminated Area
|
|
|
|
2013-06-06
|
232
|
Continuing Obligation - Residual Soil Contamination
|
|
|
|
2013-06-06
|
236
|
Continuing Obligation - Residual GW Contamination
|
|
|
|
2013-06-06
|
56
|
Continuing Obligation(s) Applied
|
|
|
|
2013-06-06
|
46
|
Impacted Right-of-Way (ROW) Notification
|
|
AUTO-POPULATED 2018-03-20
|
|
2013-05-30
|
700
|
Database Fee Paid for Groundwater Continuing Obligation(s)
|
|
REC'D CK #29205 $250.00
|
|
2013-05-30
|
710
|
Database Fee Paid for Soil Continuing Obligation(s)
|
|
REC'D CK #29205 $200.00
|
|
2013-05-30
|
779
|
Case Closure Review Fee Received
|
|
REC'D CK #29205 $750.00
|
|
2013-05-30
|
148
|
Remedial Action Design Report Received (fee)
|
|
NO FEE, REVIEWED WITH CLOSURE REQUEST AND TECHNICAL ASST
|
|
2013-05-29
|
98
|
Technical Assistance Provided
|
|
|
|
2013-05-01
|
99
|
Miscellaneous
|
|
MONTHLY PROGRESS RPT
|
|
2013-05-01
|
199
|
Additional Information Received (Fee-Based or Closure)
|
|
|
|
2013-04-16
|
99
|
Miscellaneous
|
|
PROPOSED UPLAND OU PLAN
|
|
2013-02-28
|
99
|
Miscellaneous
|
|
PROGRESS REPORT
|
|
2012-12-19
|
198
|
Request for Additional Information (Fee-Based or Closure)
|
|
ASKED RP AND CONSULTANT VIA VOICEMAIL TO SUBMIT BARRIER MAINT PLAN
|
|
2012-10-30
|
97
|
Technical Assistance Request Received (fee)
|
|
REC'D CK #900231798 $500.00
|
|
2012-10-01
|
99
|
Miscellaneous
|
|
CONCURRENCE WITH THE RECORD OF DECISION FOR WPSC CAMPMARINA
|
|
2012-08-28
|
43
|
Site Activity Status Update Received
|
|
DRAFT SEPTEMBER 2012 EPA RECORD OF DECISIONS
|
|
2012-07-02
|
43
|
Site Activity Status Update Received
|
|
|
|
2012-05-02
|
43
|
Site Activity Status Update Received
|
|
|
|
2012-03-15
|
43
|
Site Activity Status Update Received
|
|
|
|
2011-09-11
|
43
|
Site Activity Status Update Received
|
|
"WEEKLY PROGRESS REPORT"
|
|
2011-09-07
|
130
|
DNR Regulatory Reminder Sent
|
|
Vapor Intrusion (VI) Assessment Notification Ltr Sent
|
|
2011-06-29
|
99
|
Miscellaneous
|
|
CONSTRUCTION QUALITY ASSURANCE PROJECT PLAN
|
|
2011-06-24
|
147
|
Remedial Action (RA) Design Report Received (non-fee)
|
|
SEDIMENTS
|
|
2011-06-15
|
40
|
Remedial Action Options Report (RAOR) Approved
|
|
EMAILED CONCURRENCE WITH US EPA EMERGENCY REMOVAL PLAN
|
|
2011-06-01
|
311
|
Superfund Proposed Plan (PP) Issued
|
|
|
|
2011-05-19
|
99
|
Miscellaneous
|
|
REC'D RPT VPLE REVIEW MAPS, SOIL SAMPLING DATA & ANALYTICAL TABLES
|
|
2011-04-11
|
39
|
Remedial Action Options Report (RAOR) Received (non-fee)
|
|
|
|
2011-03-29
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER QUALITY DATA TRANSMITTAL
|
|
2010-08-17
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER MONITORING OK JF
|
|
2010-02-18
|
40
|
Remedial Action Options Report (RAOR) Approved
|
|
NO FORMAL APPROVAL ISSUED. PRIOR TO VPLE APPLICATION
|
|
2010-02-17
|
39
|
Remedial Action Options Report (RAOR) Received (non-fee)
|
|
OK JF
|
|
2009-07-30
|
38
|
Site Investigation Report (SIR) Approved
|
|
NO FORMAL APPROVAL ISSUED. PRIOR TO VPLE APPLICATION
|
|
2009-07-29
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
SITE INVESTIGATION REPORT FOR SEDIMENTS, APPENIDX G AND I IN DOCUMENTS MODULE
|
|
2009-04-02
|
43
|
Site Activity Status Update Received
|
|
GR0UNDWATER MONITORING REPORT
|
|
2009-01-27
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
GALARNEAU (WT) PROVIDED INPUT/RESPONSE
|
|
2009-01-05
|
43
|
Site Activity Status Update Received
|
|
|
|
2008-05-28
|
99
|
Miscellaneous
|
|
PROGRESS REPORT LETTER TO US EPA
|
|
2008-05-12
|
99
|
Miscellaneous
|
|
EPA APPROVAL LETTER FOR RI/FS WORKPLAN
|
|
2008-03-31
|
43
|
Site Activity Status Update Received
|
|
GW MONITORING REPORT.
|
|
2008-03-17
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
RI/FS FOR SEDIMENTS ON CD
|
|
2008-02-26
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
MULTI-SITE FIELD SAMPLING PLAN (SEDIMENTS UNDER US EPA)
|
|
2007-05-22
|
99
|
Miscellaneous
|
|
TERMINATION OF ERP CONTRACT. DOCUMENT INCLUDES WPSC/EPA SETTLEMENT AGREEMENT
|
|
2007-01-26
|
305
|
Superfund Enforcement Documents - See Description
|
|
ORDER ON CONSENT FOR RI/FS SIGNED
|
|
2007-01-26
|
301
|
Superfund NPL, NPL Proposed or Alternative Approach Site
|
|
|
|
2005-11-28
|
92
|
Operation & Maintenance (O&M) Report Received (non-fee)
|
|
O&M REPORT
|
|
2005-03-14
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER REPORT
|
|
2005-01-03
|
43
|
Site Activity Status Update Received
|
|
REC'D 2004 ANNAUL OPERATION, MAINTEN. & MONITORING RPT. REVIEWED BY JF 1-20-05
|
|
2004-12-22
|
92
|
Operation & Maintenance (O&M) Report Received (non-fee)
|
|
O&M REPORT
|
|
2004-08-30
|
99
|
Miscellaneous
|
|
REVIEW LETTER SENT
|
|
2004-07-20
|
97
|
Technical Assistance Request Received (fee)
|
|
|
|
2004-07-20
|
98
|
Technical Assistance Provided
|
|
|
|
2004-07-09
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
|
|
2004-01-12
|
43
|
Site Activity Status Update Received
|
|
STATUS REPORT
|
|
2003-12-31
|
92
|
Operation & Maintenance (O&M) Report Received (non-fee)
|
|
O&M REPORT
|
|
2003-03-04
|
151
|
Remedial Action (RA) Documentation Report Received (non-fee)
|
|
|
|
2003-03-04
|
151
|
Remedial Action (RA) Documentation Report Received (non-fee)
|
|
RADR APPENDIX E THROUGH APPENDIX Y
|
|
2002-04-30
|
43
|
Site Activity Status Update Received
|
|
REMEDIAL PROGRAM PLANNING UPDATE
|
|
2001-01-11
|
99
|
Miscellaneous
|
|
RECORD OF DECISION ISSUED
|
|
2000-11-14
|
99
|
Miscellaneous
|
|
REMEDIAL DESIGN REPORT PHASE 1 AND II TECH SPECS
|
|
2000-07-12
|
99
|
Miscellaneous
|
|
REMEDIAL DESIGN APPROVED
|
|
2000-04-17
|
147
|
Remedial Action (RA) Design Report Received (non-fee)
|
|
REMEDIAL DESIGN REPORT PHASE II
|
|
2000-03-30
|
99
|
Miscellaneous
|
|
PILOT TEST WORKPLAN
|
|
2000-02-23
|
43
|
Site Activity Status Update Received
|
|
PROJECT SCHEDULE UPDATE
|
|
2000-02-02
|
147
|
Remedial Action (RA) Design Report Received (non-fee)
|
|
REMEDIAL DESIGN REPORT PHASE I
|
|
2000-01-13
|
99
|
Miscellaneous
|
|
REQUEST FOR GRADING PERMIT
|
|
1999-10-25
|
40
|
Remedial Action Options Report (RAOR) Approved
|
|
MGB.
|
|
1999-05-07
|
310
|
Superfund Final Feasibility Study (FS) Submittal
|
|
FEASIBILITY STUDY
|
|
1998-12-07
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
|
|
1998-11-16
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
RIVER SEDIMENT INVESTIGATION REPORT
|
|
1996-06-28
|
29
|
Phase II Environmental Site Assessment (ESA) Rpt Received
|
|
|
|
1995-08-31
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
SEDIMENT SIWP
|
|
1994-06-27
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
|
|
1992-11-11
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
|
|
1992-06-30
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
APPENDICES
|
|
1992-06-30
|
28
|
Phase I Environmental Site Assessment (ESA) Rpt Received
|
|
PHASE I ESA RPT
|
|
1992-04-01
|
99
|
Miscellaneous
|
|
ENVIRONMENTAL REPAIR CONTRACT
|
|
1990-08-27
|
1
|
Notification of Hazardous Substance Discharge
|
|
|