ACTIVITY DETAILS

 
02-16-275446 SUPERIOR WATER LIGHT & POWER PLT (MGP)
Activity Type / Status Jurisdiction
ERP  OPEN DNR RR
Location Name County DNR Region
SUPERIOR WATER LIGHT & POWER CO DOUGLAS NORTHERN
Address Municipality
WINTER ST & USH 53 SUPERIOR
PLSS Description Latitude (WGS84) Longitude (WGS84) Google Maps RR Sites Map
SW 1/4 of the NW 1/4 of Sec 13, T49N, R14W 46.7297225 -92.0736357 Click to view on Google Maps using Lat/Long Click to View RR Sites Map
Additional Activity Details Acres
UNKNOWN
Facility ID PECFA No. EPA ID Start Date End Date
2001-11-01
Characteristics
Above Ground
Petrol Tank

Drycleaner
EPA
NPL Site
EPA
Superfund
PECFA Funds
Eligible

PFAS

ROW Impact

Sediments
Underground
Petrol Tank
WI DOT
Site
  Sediments Flag
Actions and Documents
Date Code Name File Comment
2024-03-29 39 Remedial Action Options Report (RAOR) Received (non-fee) Download PDF file RAOR RPT REC'D
2024-02-01 151 Remedial Action (RA) Documentation Report Received (non-fee) Indicates multiple files are linked to this action CONSTRUCTION COMPLETION RPT REC'D - 1 TO 4
2024-01-05 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2023 - 12/31/2023
2023-07-24 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 01/01/2023 - 06/30/2023
2023-06-29 99 Miscellaneous Download PDF file REC'D RESPONSE TO DNR'S ACCESS LTR
2023-06-20 99 Miscellaneous Download PDF file GRAYMONT/LAKEHEAD CONCRETE ACCESS LETTER
2023-06-20 99 Miscellaneous Download PDF file LAKEHEAD CONCRETE ACCESS LETTER
2023-05-15 99 Miscellaneous Download PDF file STRUCTURAL IMPEDIMENT REMOVAL INVESTIGATION & REMEDIAL ACTION PLAN REC'D
2023-05-15 99 Miscellaneous Download PDF file DNR RESPONSE TO STRUCTURAL IMPEDIMENT REMOVAL SIWP AND RAP
2023-04-14 99 Miscellaneous Download PDF file UPLAND CONSTRUCTION SCHEDULE UPDATE
2023-04-12 99 Miscellaneous Download PDF file EMAIL DISUCUSSING REMOVAL OF STRUCTURAL IMPEDIMENT, CHANGING CO'S AND ADDTIONAL INVESTIGATION
2023-04-12 37 Site Investigation Report (SIR) Received (non-fee) Download PDF file REMEDIAL INVESTIGATION SUMMARY FOR ENTIRE C STREET SLIP MGP AND MERCURY IMPACTED SEDIMENTS
2023-03-10 147 Remedial Action (RA) Design Report Received (non-fee) Indicates multiple files are linked to this action REVISED 100% DESIGN AND DESIGN FOR CONSTRUCTION RPTS REC'D
2023-03-01 99 Miscellaneous Indicates multiple files are linked to this action SHPO LETTER
2023-02-27 193 CO Modification Notice to Proceed (NTP) Download PDF file CO MOD NTP EMAIL SENT
2023-02-27 37 Site Investigation Report (SIR) Received (non-fee) Download PDF file SUPPLEMENTAL SITE INVESTIGATION RPT C STREET SLIP SEDIMENTS
2023-02-24 191 CO Modification Notification Received (non-fee) Download PDF file CO MOD NOTIFICATION REC'D
2023-01-17 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2022 - 12/31/2022
2022-12-29 56 Continuing Obligation(s) Applied Download PDF file CO APPLIED AT REMEDIAL ACTION APPROVAL - (THIS IS NOT A CLOSURE REVIEW)
2022-12-29 220 Continuing Obligation - Soil at Industrial Levels
2022-12-29 224 Continuing Obligation - Structural Impediment to Cleanup
2022-12-29 232 Continuing Obligation - Residual Soil Contamination
2022-12-29 236 Continuing Obligation - Residual GW Contamination
2022-12-29 234 Continuing Obligation - Monitoring Well Needs Abandonment - CONTINUED MONITORING IS REQUIRED AT THIS SITE
2022-12-29 226 Continuing Obligation - Vapor Intrusion Response
2022-12-29 149 Remedial Action (RA) Design Report Approved Indicates multiple files are linked to this action RAP DESIGN APPR
2022-12-28 99 Miscellaneous Download PDF file FIGURES FOR CORRECTED LOCATION OF MW-29 AND CORRECTED DEPTH OF MW-3B & 4B
2022-12-27 99 Miscellaneous Download PDF file PROPOSED MW-29 RELOCATION
2022-12-22 99 Miscellaneous Download PDF file DNR SOURCE CONTROL LETTER FOR GLNPO
2022-12-20 99 Miscellaneous Download PDF file DNR REQ - UPDATE ON BUILDING STATUS
2022-12-14 99 Miscellaneous Download PDF file SWL&P RESPONSE TO DNR'S 12/19/22 EMAIL
2022-12-09 99 Miscellaneous Download PDF file SLIP RECONTAMINATION EVALUATION REQ SENT
2022-11-29 710 Database Fee Paid for Soil Continuing Obligation(s) CK # 532767 - CO APPLIED AT REMEDIAL ACTION APPROVAL - (THIS IS NOT A CLOSURE REVIEW)
2022-11-29 700 Database Fee Paid for Groundwater Continuing Obligation(s) CK # 532767 - CO APPLIED AT REMEDIAL ACTION APPROVAL - (THIS IS NOT A CLOSURE REVIEW)
2022-11-04 99 Miscellaneous Download PDF file C STREET SLIP DATA USABILITY ASSESSMENT
2022-10-17 148 Remedial Action Design Report Received (fee) Indicates multiple files are linked to this action CK # 532751 - 100% UPLAND REMEDIAL ACITON DESIGN PART 2 OF 2
2022-09-13 99 Miscellaneous Download PDF file CITY OF SUPERIOR 100 PERCENT DESIGN COMMENTS
2022-08-15 99 Miscellaneous Download PDF file GRAYMONT COMMENTS ON SW&P UPLAND DESIGN
2022-07-26 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2022 - 6/30/2022
2022-07-07 82 Remedial Action Options Report (RAOR) Not Approved Download PDF file DNR COMMENTS ON DRAFT RAOR FOR SEDIMENTS
2022-06-03 99 Miscellaneous Download PDF file CITY OF SUPERIOR RESPONSE TO CO NOTIFICATION
2022-06-03 99 Miscellaneous Download PDF file GRAYMONT RESPONSE TO CO NOTIFICATION
2022-06-03 99 Miscellaneous Download PDF file BNSF RESPONSE TO CO NOTIFICATION
2022-05-05 143 Remedial Action Options Report (RAOR) Received (fee) Download PDF file ACH - RAOR FOR SEDIMENT
2022-05-05 99 Miscellaneous Download PDF file DNR REPSONSE TO SUGGESTED REVISIONS 90% DESIGN
2022-05-05 99 Miscellaneous OFF SITE PROPERTY OWNER NOTIFICATIONS
2022-05-05 99 Miscellaneous Download PDF file OFF SITE PROPERTY OWNER NOTIFICATIONS
2022-04-12 99 Miscellaneous 90 PERCENT DESIGN NEW DRAFT
2022-04-07 99 Miscellaneous Download PDF file DNR RESPONSE TO SWL&P 3/29/20 SBMITTAL
2022-04-01 99 Miscellaneous Download PDF file MARCH 31, 2022 MEETING SLIDES
2022-03-29 99 Miscellaneous Download PDF file SWL&P RESONSE TO DNR'S 90 PERCENT DESIGN COMMENTS
2022-03-10 99 Miscellaneous Download PDF file DRAFT CO NOTIFICATIONS
2022-03-10 99 Miscellaneous DNR COMMENTS ON DRAFT CO NOTIFICATIONS
2022-03-07 99 Miscellaneous Download PDF file 03-07-22 DNR SWL&P GLNPO MEETING PRESENTATION
2022-03-04 99 Miscellaneous Download PDF file 02-07-22 DNR SWL&P GLNPO MEETING PRESENTATION
2022-03-03 99 Miscellaneous Download PDF file SEDIMENT PRE DESIGN INVESTIGATION RESULTS
2022-01-26 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2021 - 12/31/2021
2021-12-23 150 Remedial Action (RA) Design Report Not Approved Download PDF file RAP NOT APPROVED - 90% DESIGN REPORT REVIEW DNR COMMENTS
2021-12-03 99 Miscellaneous USPS DOCUMENTATION AND DNR RESPONSE
2021-11-08 99 Miscellaneous Download PDF file WIS STATS & ADMIN CODE
2021-10-22 99 Miscellaneous Download PDF file DNR EMAIL REQUESTING PIEZOMETERS
2021-10-01 99 Miscellaneous Download PDF file SLIDES FROM 9/22/21 MEETING
2021-09-27 99 Miscellaneous Download PDF file INJECTION EXEMPTION EVALUATION
2021-09-14 148 Remedial Action Design Report Received (fee) Download PDF file ACH
2021-08-12 99 Miscellaneous Download PDF file 60 RAP PERCENT DESIGN NOTICE TO PROCEED
2021-07-23 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2021 - 6/30/2021
2021-05-24 99 Miscellaneous Download PDF file SWL&P RESPONSE TO DNR COMMENTS ON 60% DESIGN REPORT
2021-04-20 149 Remedial Action (RA) Design Report Approved Download PDF file 60 PERCENT DESIGN REPORT DNR COMMENTS
2021-04-06 130 DNR Regulatory Reminder Sent Download PDF file VAPOR INTRUSION AND TCE REMINDER LETTER
2021-03-23 148 Remedial Action Design Report Received (fee) Download PDF file ACH
2021-01-28 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2020 - 12/31/2020
2021-01-28 40 Remedial Action Options Report (RAOR) Approved Download PDF file RAOR APPR - UPLAND AREA
2021-01-21 99 Miscellaneous Download PDF file FIGURE SHOWING PROPOSED PAH EXCAVATION AREA
2021-01-08 143 Remedial Action Options Report (RAOR) Received (fee) Download PDF file FINAL RAOR REC'D - NO FEE
2021-01-08 99 Miscellaneous Download PDF file DNR COMMENTS ON PROPOSED GLLA PROJECT
2020-12-14 99 Miscellaneous Download PDF file FOTH PRESENTATION FOR 12-14-20 MEETING
2020-12-07 99 Miscellaneous Download PDF file FOTH PRESENTATION FOR 12-7-20 MEETING
2020-12-01 82 Remedial Action Options Report (RAOR) Not Approved Download PDF file RAOR NOT APPR
2020-12-01 99 Miscellaneous Download PDF file PRE DESIGN INVESTIGATION BORING LOGS
2020-11-30 99 Miscellaneous Download PDF file GROUNDWATER FORMS AND FIELD NOTES
2020-11-16 143 Remedial Action Options Report (RAOR) Received (fee) Download PDF file CK # 7912 - (DRAFT RAOR)
2020-08-27 99 Miscellaneous Download PDF file PDI INVESTIGATION BORING ABANDONMENT FORMS
2020-08-17 130 DNR Regulatory Reminder Sent Download PDF file EMERGING CONTAMINANTS REMINDER LETTER
2020-07-15 99 Miscellaneous Download PDF file REDESIGN INVESTIGATION UPDATE AND DNR RESPONSE
2020-07-15 99 Miscellaneous PDI STATUS UPDATE
2020-07-09 99 Miscellaneous Download PDF file PDI FIELDWORK UPDATE & MODIFICATIONS
2020-07-08 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2020 - 6/30/2020
2020-07-06 99 Miscellaneous Download PDF file PDI SCOPE MODIFICATION DNR EMAIL
2020-07-02 99 Miscellaneous Download PDF file PDI SCOPE MOFICIATION
2020-04-06 99 Miscellaneous Download PDF file SEDIMENT INVESTIGATION RESULTS
2020-04-03 99 Miscellaneous Download PDF file DNR EMAIL TO SWL&P
2020-03-17 99 Miscellaneous Download PDF file SWLP RESPONSE LTR REC'D
2020-03-02 98 Technical Assistance Provided Download PDF file PRE-DESIGN WORK PLAN APPROVAL
2020-02-07 97 Technical Assistance Request Received (fee) Download PDF file ACH - TECH ASSIST PRE-DESIGN INVESTIGATION WP REC'D
2020-01-08 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2019 - 12/31/2019
2019-11-27 99 Miscellaneous Download PDF file DRAFT PRE-DESIGN INVESTIGATION WP REC'D
2019-10-18 99 Miscellaneous Download PDF file WORK SCHEDULE CHANGE NOTICE REC'D
2019-07-25 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2019 - 6/30/2019
2019-06-27 38 Site Investigation Report (SIR) Approved Download PDF file SIR APPROVED
2019-06-04 199 Additional Information Received (Fee-Based or Closure) Download PDF file SIR CLARIFICATION REC'D
2019-04-29 198 Request for Additional Information (Fee-Based or Closure) ADDT'L INFO REQ
2019-03-28 137 Site Investigation Report (SIR) Received (fee) Download PDF file ACH PAYMENT REC'D
2019-03-27 37 Site Investigation Report (SIR) Received (non-fee) Download PDF file SITE INVESTIGATION RPT REC'D - 1 OF 2
2019-03-27 99 Miscellaneous Download PDF file SITE INVESTIGATION RPT REC'D 2 OF 2
2019-01-24 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2018 - 12/31/2018
2018-07-02 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2018 - 6/30/2018
2018-01-03 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2017 - 12/31/2017
2017-12-08 38 Site Investigation Report (SIR) Approved Download PDF file
2017-11-14 199 Additional Information Received (Fee-Based or Closure) Download PDF file INFO REC'D
2017-11-14 99 Miscellaneous Download PDF file REC'D CORRESPONDENCE FROM RP RE: LIMESTONE CLARIFICATION
2017-11-13 99 Miscellaneous Download PDF file DNR SUPPLEMENTAL SITE INVESTIGATION COMMENTS
2017-10-30 198 Request for Additional Information (Fee-Based or Closure) ADDT'L INFO REQUESTED
2017-09-20 137 Site Investigation Report (SIR) Received (fee) Download PDF file CK # 4157
2017-07-17 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2017 - 6/30/2017
2017-03-06 97 Technical Assistance Request Received (fee) CK # 190731
2017-03-06 98 Technical Assistance Provided LTR SENT 11/14/16
2017-01-20 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2016 - 12/31/2016
2016-11-14 99 Miscellaneous Download PDF file SOIL MGMT APPROVAL LTR SENT
2016-11-10 99 Miscellaneous Download PDF file CONTAMINATED SOIL MANAGEMENT PLAN
2016-09-12 36 Site Investigation Workplan (SIWP) Approved Download PDF file SI WORK PLAN APPROVAL
2016-09-02 135 Site Investigation Workplan (SIWP) Received (fee) Download PDF file CK # 3880
2016-08-03 99 Miscellaneous Download PDF file REMEDIAL DESIGN INVESTIGATION WORK PLAN
2016-07-18 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2016 - 6/30/2016
2016-02-01 99 Miscellaneous Download PDF file EPA SITE CHARACTERIZATION RPT - SUPERIOR WATERFRONT
2016-01-29 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2015 - 12/31/2015
2015-07-21 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2015 - 6/30/2015
2015-03-01 43 Site Activity Status Update Received Download PDF file 2013 - 2014 GW MONITORING RPT REC'D - DRAFT
2015-01-06 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2014 - 12/31/2014
2015-01-06 99 Miscellaneous Download PDF file NR700 SEMI ANNUAL REPORT CONFIRMATION
2014-11-21 99 Miscellaneous Download PDF file DNR DREDGING EMAIL CORRESPNDENCE
2014-11-03 99 Miscellaneous Download PDF file DNR EMAIL AOC SITE RANKING
2014-09-15 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2014 - 6/30/2014
2013-09-03 98 Technical Assistance Provided Download PDF file REVIEW LTR SENT
2013-06-24 97 Technical Assistance Request Received (fee) CK # 103796
2013-01-15 43 Site Activity Status Update Received Download PDF file 2012 ANNUAL GW MONITORING RPT
2012-06-15 43 Site Activity Status Update Received Download PDF file 2011 ANNUAL GW MONITORING RPT
2011-09-07 130 DNR Regulatory Reminder Sent Download PDF file Vapor Intrusion (VI) Assessment Notification Ltr Sent
2011-05-31 99 Miscellaneous Download PDF file DNR REVIEW OF PROPOSED RAP
2011-03-04 99 Miscellaneous Download PDF file MONITORING WELL ABANDONMENT FORMS
2011-02-10 43 Site Activity Status Update Received Download PDF file GW MONITORING RPT
2010-06-10 99 Miscellaneous Download PDF file RESPONSE TO SEDIMENT RESULTS - DNR REVIEW OF SEDIMENT INVESTIGATION
2010-04-06 37 Site Investigation Report (SIR) Received (non-fee) Download PDF file SEDIMENT INVESTIGATION RESULTS
2009-11-04 43 Site Activity Status Update Received GW MONITORING RPT
2009-10-27 99 Miscellaneous Download PDF file GW MONITORING REPORT RECD.
2009-07-06 151 Remedial Action (RA) Documentation Report Received (non-fee) Download PDF file SOIL EXCAVATION REMEDIAL ACTION COMPLETION RPT REC'D
2008-04-07 143 Remedial Action Options Report (RAOR) Received (fee) Download PDF file $500 SUPERIOR WATER LIGHT $& POWER CHECK # 84218 RECD. DUNN
2008-03-10 39 Remedial Action Options Report (RAOR) Received (non-fee) Indicates multiple files are linked to this action REPORT SUBMITTED ON CD
2007-07-01 37 Site Investigation Report (SIR) Received (non-fee) PHASE 2 PART 4
2007-06-21 37 Site Investigation Report (SIR) Received (non-fee) Download PDF file PHASE II, PART IV OF SITE INVESTIGATION
2006-12-04 43 Site Activity Status Update Received Download PDF file
2006-12-04 43 Site Activity Status Update Received
2005-10-04 97 Technical Assistance Request Received (fee) $500 SUPERIOR WATER LIGHT & POWER CO CHECK # 75427. DUNN.
2005-10-04 98 Technical Assistance Provided $500 SUPERIOR WATER LIGHT & POWER CO CHECK # 75427. DUNN.
2005-09-26 99 Miscellaneous Download PDF file REVIEW FEE COVER LETTER
2005-09-13 35 Site Investigation Workplan (SIWP) Received (non-fee) Download PDF file WP FOR PHASE II, PART IV
2005-04-01 37 Site Investigation Report (SIR) Received (non-fee) Download PDF file FINAL REPORT FOR PHASE II & III
2004-10-01 43 Site Activity Status Update Received Download PDF file ACCESS AGREEMENTS OBTAINED
2004-03-26 37 Site Investigation Report (SIR) Received (non-fee) Download PDF file SEDIMENT SI. ONE HARD COPY, ONE ELECTRONIC COPY
2003-12-19 35 Site Investigation Workplan (SIWP) Received (non-fee)
2003-12-18 99 Miscellaneous Download PDF file SITE INVESTIGATION WP - COVER LETTER
2003-11-21 99 Miscellaneous Download PDF file RECOMMENDATIONS FOR FURTHER INVESTIGATION
2003-03-03 35 Site Investigation Workplan (SIWP) Received (non-fee) Download PDF file RPT #6 - SEDIMENT INVESTIGATION WORK PLAN-ENSR
2003-02-21 99 Miscellaneous RPT #9 - COMPARATIVE ANALYSIS OF EIGHT SOIL SAMPLES - GTI
2003-02-21 37 Site Investigation Report (SIR) Received (non-fee) Download PDF file SIR - PHASE II, PART II
2003-02-21 37 Site Investigation Report (SIR) Received (non-fee) Download PDF file SIR APPENDICES- PHASE II, PART II
2003-02-20 35 Site Investigation Workplan (SIWP) Received (non-fee) SIR RCVD ENSR CONSULTANTS
2003-02-19 37 Site Investigation Report (SIR) Received (non-fee) RPT #7 - VOL I, PHASE II, PART II SITE INVESTIGATION REPORT
2003-02-10 99 Miscellaneous Download PDF file GTI CHEMICAL FINGERPRINTING
2003-02-07 37 Site Investigation Report (SIR) Received (non-fee) RPT #8 - VOL II, PHASE II, PART II - FORENSIC APPENDICES A-F - GTI
2003-02-01 99 Miscellaneous Download PDF file GTI COMPARATIVE ANALYSIS
2002-07-17 99 Miscellaneous RPT#5 PHASE II, PART II WORKPLAN
2002-07-17 35 Site Investigation Workplan (SIWP) Received (non-fee) Download PDF file SIWP PHASE 2, PART 2
2002-05-13 43 Site Activity Status Update Received Download PDF file RPT #4 - GROUNDWATER MONITORING REPORT
2002-03-28 99 Miscellaneous Download PDF file RP NOTICE ACKNOWLEDGMENT OF RECEIPT - SWL & P
2002-02-21 2 Responsible Party (RP) letter sent Download PDF file
2002-01-23 37 Site Investigation Report (SIR) Received (non-fee) Download PDF file SIR REC'D
2002-01-10 99 Miscellaneous WILL SEND WP FOR NEXT STAGE
2002-01-01 29 Phase II Environmental Site Assessment (ESA) Rpt Received RPT #3 - PHASE II SITE INVESTIGATION REPORT.ENSR
2001-11-02 35 Site Investigation Workplan (SIWP) Received (non-fee) Download PDF file SIWP REC'D
2001-11-01 1 Notification of Hazardous Substance Discharge Download PDF file
2001-11-01 28 Phase I Environmental Site Assessment (ESA) Rpt Received Download PDF file RPT #1- PHASE I ESA REPORT.ENSR
2001-11-01 99 Miscellaneous Download PDF file RPT #2 - PHASE II INVESTIGATION WORK PLAN.ENSR
2001-08-15 99 Miscellaneous SPILL REPORT
2001-08-01 99 Miscellaneous Download PDF file SITE HISTORY
2001-06-28 99 Miscellaneous Download PDF file MEETING SUMMARY
2001-06-26 99 Miscellaneous Download PDF file DNR MEMO RE: 02-16-000014
2001-05-30 99 Miscellaneous Download PDF file DNR MEETING INVITATION
2001-03-08 99 Miscellaneous Download PDF file DNR MEMO
2001-01-11 99 Miscellaneous Download PDF file DNR MEMO
2001-01-11 99 Miscellaneous Download PDF file DNR PRELIMINARY SEDIMENT EVALUATION
2001-01-02 99 Miscellaneous Download PDF file DNR MEMO
2000-11-08 99 Miscellaneous Download PDF file WSLOH LAB REPORTS REC'D
2000-09-19 99 Miscellaneous Download PDF file WSLOH LAB REPORTS REC'D
2000-07-27 99 Miscellaneous Download PDF file DNR SEDIMENT SAMPLING MEMO
2000-07-12 99 Miscellaneous Download PDF file 1994 EPA SAMPLING SUMMARY
2000-05-23 99 Miscellaneous Download PDF file SUPERIOR WWTP GEOTECHNICAL EXPLORATION
1997-12-01 99 Miscellaneous Download PDF file USPA SEDIMENT ASSESSMENT OF HOTSPOT AREAS IN THE DULUTH/SUPERIOR HARBOR
Relationships to Other Activities
Click Activity Below to View Details
Type Related Activity
ERP to Spill 04-16-588178 SUPERIOR WATER LIGHT AND POWER SPILL
Monitoring Well Remains at Closure
Reasons when Action Code 234 is Present
CONTINUED MONITORING IS REQUIRED AT THIS SITE
Substances
Substance Type Amt Released Units
Polynuclear Aromatic Hydrocarbons Petroleum
Polynuclear Aromatic Hydrocarbons (coal tar) Petroleum
Volatile Organic Compounds VOC
Vapor Intrusion Continuing Obligation(s)
(B) Compounds of Concern in Use – Commercial/Industrial Restriction: Property use restricted to commercial or industrial. Notification of DNR required for change in property use to residential use. Vapor evaluation is required. Further cleanup may be required.
(E) Future Redevelopment of Property – Vapor Control Technology Required for Construction: DNR requires notification prior to new building construction or building modifications. Potential for vapor intrusion exists due to residual contamination. Vapor control technologies are required to be installed or modified, and verified protective unless a vapor evaluation is accepted by DNR.
Responsible Party
JAMISON MEHLE 2915 HILL AVE, SUPERIOR, WI 54880
SUPERIOR WATER LIGHT & POWER 2915 HILL AVE, SUPERIOR, WI 54880
DNR Project Manager
JOHN SAGER  john.sager@wisconsin.gov
275446 | 02-16-275446