Watershed - Upper East Branch Pecatonica River (SP06)
Upper East Branch Pecatonica River Watershed

Details

The Upper East Branch Pecatonica River Watershed lies in eastern Iowa County and a very small portion of western Dane County. Over half of the land use in the watershed is agricultural with some woodlots along valleys and creeks. Four municipalities border the northern edge of the watershed and discharge to surface waters within the watershed. The village of Hollandale also lies in the southcentral portion of the watershed and discharges to the Dodge Branch. Despite the presence of these municipalities, the population of the watershed is likely to only grow by about 8% over the next 20 years. However, development along the northern edge of the watershed could affect the water quality of some of the headwater streams. Although there are problems caused by non-point source pollution and streambank pasturing, there are 13 streams in the watershed with portions of their length able to support trout. Excess sedimentation and habitat degradation are the major impacts in the watershed.

Date  2002

Ecological Landscapes for Upper East Branch Pecatonica River Watershed

Ecological Landscapes

The Southwest Savanna Ecological Landscape is located in the far southwestern part of the state. It is characterized by deeply dissected topography, unglaciated for the last 2.4 million years, with broad open hilltops and river valleys, and steep wooded slopes. The climate is favorable for agriculture but the steep slopes limit it to the hilltops and valley bottoms. Soils are underlain with calcareous bedrock. Soils on hilltops are silty loams, sometimes of shallow depth over exposed bedrock and stony red clay subsoil. Some valley soils are alluvial sands, loams, and peats. Some hilltops are almost treeless due to the thin soil while others have a deep silt loam cap. Historic vegetation consisted of tall prairie grasses and forbs with oak savannas and some wooded slopes of oak. Almost three-quarters of the current vegetation is agricultural crops with lesser amounts of grasslands, barrens, and urban areas. The major forest types are oak-hickory and maple-basswood. High-quality prairie remnants occur on rocky hilltops and slopes that are not farmed. Some prairie pastures and oak savannas still exist. The grassland areas harbor many rare grassland birds, invertebrates, and other grassland species. Relict stands of pine occur on bedrock outcroppings along some stream systems.

Date  2010

Watershed Documents
Watershed Grants
Grant Details
Aquatic Invasives Early Detection and Response
Date
5/5/2008
Waters Involved
Williams-Barneveld Creek
Status
Complete

The Prairie Enthusiasts, Inc.: Preventing Spread Of Reed Canary Grass & Watercress-Williams Barneveld Creek: The Prairie Enthusiasts will sponsor a project along the Williams-Barneveld Creek. This overall project goal is to prevent pioneer populations of reed canary grass and watercress from reproducing and/or expanding. Project deliverables include: 1)treatment of existing populations; 2) monitoring and scouting for additional seedlings; 3) suppression and control activities; 4) recover, maintain and enhance original vegetation community; 5) document and educate the public through written newsletters of this aquatic invasive species effort.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Barbian Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Barbian Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Bass Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Bass Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Brandenburg Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Brandenburg Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Carl Buechner Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Carl Buechner Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Cherokee Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Cherokee Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Crystal Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Crystal Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Diedrich Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Diedrich Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Fish Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Fish Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Fishers Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Fishers Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Goose Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Goose Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Graber Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Graber Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Grass Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Grass Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Hook Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Hook Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Indian Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Indian Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Island Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Island Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Kalscheur Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Kalscheur Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Barney
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Barney
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Belle View
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Belle View
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Harriett
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Harriett
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Kegonsa
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Kegonsa
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Koshkonong
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Koshkonong
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Mendota
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Mendota
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Monona
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Monona
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Waubesa
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Waubesa
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Wingra
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Wingra
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Louis Buechner Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Louis Buechner Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Maher Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Maher Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Marshall Millpond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Marshall Millpond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Maunesha Flowage
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Maunesha Flowage
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Meier Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Meier Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Morse Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Morse Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Mortenson Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Mortenson Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Mud Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Mud Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Rice Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Rice Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Rockdale Millpond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Rockdale Millpond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Salmo Pond (Raemisch Pond)
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Salmo Pond (Raemisch Pond)
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Springfield Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Springfield Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Stebbinsville Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Stebbinsville Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Stewart Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Stewart Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Stoughton Millpond 429
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Stoughton Millpond 429
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Strickers Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Strickers Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Tenney Park Lagoon
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Tenney Park Lagoon
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Tiedemans Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Tiedemans Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Unnamed
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Unnamed
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Upper Mud Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Upper Mud Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Verona Gravel Pit
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Verona Gravel Pit
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Virgin Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Virgin Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Windsor Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Windsor Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Barbian Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Bass Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2008
Waters Involved
Birch Lake
Status
Complete

Village Of Barneveld: Birch Lake Diagnostic Study-Pt. 1: The Village of Barneveld proposes to complete a diagnostic study on Birch Lake, Iowa County, to assess current water quality conditions and use impairments. The project activities include: 1. estimating nutrient and sediment inputs, 2. assessing in-lake conditions and 3. assessing current condition of the outlet structure, and potential impacts to both impoundment and trout stream below the dam. Deliverables for this grant include a water resources appraisal report as part of the overall lake management plan, and all applicable ranking question deliverables. The DNR will be provided with both a paper copy and an editable electronic copy of the final report. The project results will be disseminated to the public by local newspaper and public meetings.


Grant Details
Large Scale Lake Planning
Date
10/1/2008
Waters Involved
Birch Lake
Status
Complete

Village Of Barneveld: Birch Lake Feasibility Study-Pt. 2: The Village of Barneveld proposes to complete a Feasibility study on Birch Lake, Iowa County, to develop a comprehensive management plan for lake restoration. The project activities include: 1. present diagnostic findings at a public meeting and discuss management options, 2. solicit comments and responses from a user survey, and 3. prepare final plan with recommended management and restoration. Deliverables for this grant include 1. a copy of the user survey, 2. the final management plan, and 3. all applicable ranking question deliverables. The DNR will be provided with both a paper copy and an editable electronic copy of the final report. The project results will be disseminated to the public by sharing the final document with NRCS, Iowa County LCD, and fact sheets shared with the public and media.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Brandenburg Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Carl Buechner Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Cherokee Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Crystal Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Diedrich Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Fish Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Fishers Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Goose Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Graber Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Grass Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Hook Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Indian Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Island Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Kalscheur Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Barney
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Belle View
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Harriett
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Kegonsa
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Koshkonong
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Mendota
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Monona
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Waubesa
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Wingra
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Louis Buechner Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Maher Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Marshall Millpond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Maunesha Flowage
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Meier Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Morse Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Mortenson Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Mud Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Rice Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Rockdale Millpond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Salmo Pond (Raemisch Pond)
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Springfield Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Stebbinsville Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Stewart Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Stoughton Millpond 429
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Strickers Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Tenney Park Lagoon
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Tiedemans Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2008
Waters Involved
Trout Creek
Status
Complete

Village Of Barneveld: Birch Lake Diagnostic Study-Pt. 1: The Village of Barneveld proposes to complete a diagnostic study on Birch Lake, Iowa County, to assess current water quality conditions and use impairments. The project activities include: 1. estimating nutrient and sediment inputs, 2. assessing in-lake conditions and 3. assessing current condition of the outlet structure, and potential impacts to both impoundment and trout stream below the dam. Deliverables for this grant include a water resources appraisal report as part of the overall lake management plan, and all applicable ranking question deliverables. The DNR will be provided with both a paper copy and an editable electronic copy of the final report. The project results will be disseminated to the public by local newspaper and public meetings.


Grant Details
Large Scale Lake Planning
Date
10/1/2008
Waters Involved
Trout Creek
Status
Complete

Village Of Barneveld: Birch Lake Feasibility Study-Pt. 2: The Village of Barneveld proposes to complete a Feasibility study on Birch Lake, Iowa County, to develop a comprehensive management plan for lake restoration. The project activities include: 1. present diagnostic findings at a public meeting and discuss management options, 2. solicit comments and responses from a user survey, and 3. prepare final plan with recommended management and restoration. Deliverables for this grant include 1. a copy of the user survey, 2. the final management plan, and 3. all applicable ranking question deliverables. The DNR will be provided with both a paper copy and an editable electronic copy of the final report. The project results will be disseminated to the public by sharing the final document with NRCS, Iowa County LCD, and fact sheets shared with the public and media.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Unnamed
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2008
Waters Involved
Unnamed
Status
Complete

Village Of Barneveld: Birch Lake Diagnostic Study-Pt. 1: The Village of Barneveld proposes to complete a diagnostic study on Birch Lake, Iowa County, to assess current water quality conditions and use impairments. The project activities include: 1. estimating nutrient and sediment inputs, 2. assessing in-lake conditions and 3. assessing current condition of the outlet structure, and potential impacts to both impoundment and trout stream below the dam. Deliverables for this grant include a water resources appraisal report as part of the overall lake management plan, and all applicable ranking question deliverables. The DNR will be provided with both a paper copy and an editable electronic copy of the final report. The project results will be disseminated to the public by local newspaper and public meetings.


Grant Details
Large Scale Lake Planning
Date
10/1/2008
Waters Involved
Unnamed
Status
Complete

Village Of Barneveld: Birch Lake Feasibility Study-Pt. 2: The Village of Barneveld proposes to complete a Feasibility study on Birch Lake, Iowa County, to develop a comprehensive management plan for lake restoration. The project activities include: 1. present diagnostic findings at a public meeting and discuss management options, 2. solicit comments and responses from a user survey, and 3. prepare final plan with recommended management and restoration. Deliverables for this grant include 1. a copy of the user survey, 2. the final management plan, and 3. all applicable ranking question deliverables. The DNR will be provided with both a paper copy and an editable electronic copy of the final report. The project results will be disseminated to the public by sharing the final document with NRCS, Iowa County LCD, and fact sheets shared with the public and media.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Upper Mud Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Verona Gravel Pit
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Virgin Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Windsor Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Barbian Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Barbian Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Bass Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Bass Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Brandenburg Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Brandenburg Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Carl Buechner Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Carl Buechner Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Cherokee Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Cherokee Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Crystal Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Crystal Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Diedrich Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Diedrich Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Fish Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Fish Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Fishers Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Fishers Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Goose Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Goose Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Graber Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Graber Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Grass Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Grass Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Hook Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Hook Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Indian Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Indian Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Island Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Island Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Kalscheur Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Kalscheur Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Barney
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Barney
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Belle View
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Belle View
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Harriett
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Harriett
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Kegonsa
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Kegonsa
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Koshkonong
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Koshkonong
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Mendota
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Mendota
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Monona
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Monona
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Waubesa
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Waubesa
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Wingra
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Wingra
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Louis Buechner Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Louis Buechner Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Maher Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Maher Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Marshall Millpond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Marshall Millpond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Maunesha Flowage
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Maunesha Flowage
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Meier Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Meier Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Morse Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Morse Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Mortenson Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Mortenson Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Mud Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Mud Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Rice Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Rice Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Rockdale Millpond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Rockdale Millpond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Salmo Pond (Raemisch Pond)
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Salmo Pond (Raemisch Pond)
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Springfield Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Springfield Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Stebbinsville Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Stebbinsville Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Stewart Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Stewart Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Stoughton Millpond 429
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Stoughton Millpond 429
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Strickers Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Strickers Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Tenney Park Lagoon
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Tenney Park Lagoon
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Tiedemans Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Tiedemans Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Unnamed
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Unnamed
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Upper Mud Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Upper Mud Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Verona Gravel Pit
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Verona Gravel Pit
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Virgin Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Virgin Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Windsor Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Windsor Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Targeted Runoff - Rural Construction
Date
9/7/2004
Waters Involved
Ley Creek
Status
Complete

Iowa County Lcd: Ley Creek Habitat Improvement: streambank remediation practices along Ley Creek within DNR eased properties


Grant Details
Urban Nonpoint - Stormwater Planning
Date
1/1/2004
Waters Involved
Dodge Br
Status
Complete

City Of Dodgeville: Stormwater Utility Analysis: to cost-share @70% analysis & formation of stormwater utility district


Grant Details
River Planning Grant
Date
7/1/2010
Waters Involved
Unnamed
Status
Complete

The Prairie Enthusiasts, Inc.: Wq Assessment Of Mounds View Creek: The Prairie Enthusiasts will sponsor a project on the Mounds View Creek, in the Town of Brigham, Iowa County. The goals of this project include ecological restoration, education and capacity building as terrestrial volunteers expand their focus to this small stream. Project deliverables include: 1) preparation of a stream corridor restoration plan that identifies management goals that could potentially include establishing native brook trout or redside dace population, 2.) tracking of potential water quality and stream ecological changes that coincide with the landscape scale restoration, and enter the gathered data into the DNR volunteer stream monitoring database.3.) establishing a team of volunteers to conduct routine water quality surveys along with the assistance of a licensed hydrologist, 4.) hiring an intern to conduct and intensive stream habitat evaluation and to prepare a stream restoration plan based on the habitat, water quality and biota information, and 5.) demonstrate the ecological connections between upland and riparian management with environmental health of the stream.


Grant Details
River Protection Grant
Date
7/1/2005
Waters Involved
East Branch Pecatonica River
Status
Complete

The Nature Conservancy: Restoring The Riparian...Pecatonica: The project will take place in the Military Ridge Prairie Heritage Area. The diverse partnership of conservation organizations are protecting and restoring a patchwork of prairies and other grassland habitats along the Dane and Iowa County border. The main intent of the restoration work described in this proposal is to return a stretch of the East Branch of the Pecatonica River and its flood plain to as close to its pre-European settlement condition as possible.

A full description of the project goal and objectives are in the grant application, which is a part of this application. The DNR will be provided with both a paper copy and an electronic copy of the final report. Information will be disseminated to the public as described in the grant application.


Grant Details
River Protection Grant
Date
7/1/2010
Waters Involved
Williams-Barneveld Creek
Status
Complete

The Prairie Enthusiasts, Inc.: Shea Prairie Stream & Wetland Restoration: The Prairie Enthusiasts will sponsor a project to restore the Williams-Barneveld stream channel and floodplain located within the Military Ridge Prairie Heritage Area to pre-European settlement condition. Project deliverables include: 1) continuing stream baseline geomorphology study, completion of soil borings to determine depth of alluvial depositions and ground water hydrology, completion of cross sections of stream channel and floodplain for engineering plans, continuation of herptile surveys for baseline information, completion of a vegetation survey of excavation area not in agriculture for saving to re-vegetate with local genotypes, excavation of floodplains deposition exposing the historic floodplain soil, establishment of native wet prairie/wetland vegetation on floodplain and streambank and continuation of monitoring to measure project success.


Monitoring & Projects

Projects including grants, restoration work and studies shown below have occurred in this watershed. Click the links below to read through the text. While these are not an exhaustive list of activities, they provide insight into the management activities happening in this watershed.

Grants and Management Projects
Upper East Branch Pecatonica River Watershed
Watershed Recommendations
Monitor Water Quality or Sediment
Dodge Branch TP
Date
Status
Category 4A. 2018 TP Results: May Exceed. Station 253098. AU: 13747.
1/1/2018
Proposed
Projects
 
Upper East Branch Pecatonica River WatershedWatershed History Note

A large portion of the 41-mile Military Ridge State Trail runs through the watershed of the Upper East Branch of the Pecatonica River in Dane and Iowa counties. Most of the trail follows the former Chicago and North Western Railway line, which has a gentle grade of only 2 to 5 percent. Between Dodgeville and Mount Horeb it goes along the top of the Military Ridge, the divide between the Wisconsin River watershed to the north and the Pectonica and Rock River watersheds to the south. Between Mount Horeb and Verona it goes through the Sugar River Valley. The high point on the trail is at Blue Mounds, about 1300 feet above sea level, and the lowest is along the Sugar River between Riley and Verona, about 930 feet. The trail's name can be traced to its original purpose. After receiving numerous petitions from Wisconsin citizens and military officials, Congress appropriated $5,000 in 1832 for laying out and opening a military road to link Fort Howard in Green Bay, Fort Winnebago in Portage and Fort Crawford in Prairie du Chien. The western section of the road passed mainly on the ridge, a strategic route because the views to north and south gave military control of southwest Wisconsin. It connected with roads to Galena, Illinois, which had been opened by the lead miners. Military companies averaging 40 men each were assigned in rotation to prepare stretches of about 15 miles apiece. Each company camped out on the job, moving on as work progressed. Each probably spent about four to six weeks in the field. The work served as training for the troops in camping, cooking, and marching. The troops cleared brush two rods wide, plowed two furrows to mark the 30-feet roadway, and put crosswise logs, called corduroy, over marshy spots. Small trees were cut off close to the ground, and larger stumps were left one foot high. Rough bridges were built over some streams. Other streams just had their banks cut so travelers could splash through. In 1839, Capt. Thomas Jefferson Cram of the U.S. Army asked for more funds. "Between Madison and the Mississippi, nature has done so much towards providing a good road that an expenditure of about $10,000 in bridging the streams, ditching, and grading would be sufficient," he wrote. Despite Cram's request, no more appropriations were made until 1845. In the late 1800's the emphasis in Wisconsin moved from roads to railroads and a series of tracks were laid down to accommodate both daily passenger and freight trains over the route. Eventually the preferred mode of transportation shifted back to roads and the last passenger trains were discontinued in the 1950's. During the 1970's studies and negotiations on sections of the railroad line took place for the purpose of creating a recreational trail. By the mid 1980's, Wisconsin Conservation crews were working on the trail. They cut brush the entire length, fenced about ten miles to keep cattle off the trail, planked and railed the 48 trestles, surfaced the trail, erected signs, and built parking lots at Verona and Dodgeville. This was one of the first three projects of the Wisconsin Conservation Corps (WCC), established by the Legislature in 1983. The dedication of the completed portions of the trail was held May 19, 1985 in Barneveld.

Date  2011