Watershed - Roxbury Creek (LW18)
Roxbury Creek Watershed

Details

The Roxbury Creek Watershed lies mostly in northwest Dane County although a small portion of it extends into Columbia County. Land use in the watershed is predominantly agricultural, although a good percentage of the watershed is covered by broad-leaf deciduous forest. There are no incorporated municipalities in the watershed.

Date  2002

Population, Land Use

Overall population in the watershed in 2000 was estimated to be around 5,500 people. Residential development in the watershed is increasing as a result of the watershed's proximity to Madison.

Date  2002

Nonpoint and Point Sources

The major known water quality problems in the watershed are from nonpoint source pollution. The Roxbury Creek watershed is ranked as a high priority for nonpoint source pollution reduction. The Dunlap Creek sub-watershed was chosen as a small-scale nonpoint source pollution abatement project. Streams in the watershed are also impacted by stream channelization and portions of Dunlap Creek have been extensively channeled. Development pressure in the watershed could pose a threat to water quality in the watershed. In addition, a portion of the watershed is in an atrazine prohibition area. These areas indicate that elevated levels of atrazine, an herbicide used on corn, has been found in some tested private water wells. Soils are permeable which has allowed atrazine to reach groundwater in some locations. The Crystal Lake Campground discharges to groundwater in the watershed and the Roxbury Sewerage District discharges to Roxbury Creek.

Date  2002

Ecological Landscapes for Roxbury Creek Watershed

Ecological Landscapes

The western half of the Roxbury Watershed is located in the Western Coolee and Ridges Ecological Landscape and the eastern half is located within the Central Sand Hills Ecological Landscape. The Western Coulee and Ridges Ecological Landscape in southwestern and west central Wisconsin is characterized by its highly eroded, driftless topography and relatively extensive forested landscape. Soils are silt loams (loess) and sandy loams over sandstone residuum over dolomite. Several large rivers including the Wisconsin, Mississippi, Chippewa, Kickapoo and Black flow through or border the Ecological Landscape. Historical vegetation consisted of southern hardwood forests, oak savanna, scattered prairies, and floodplain forests and marshes along the major rivers. With Euro-American settlement, most of the land on ridgetops and valley bottoms was cleared of oak savanna, prairie, and level forest for agriculture. The steep slopes between valley bottom and ridgetop, unsuitable for raising crops, grew into oak-dominated forests after the ubiquitous presettlement wildfires were suppressed. Current vegetation is a mix of forest (40%), agriculture, and grassland with some wetlands in the river valleys. The primary forest cover is oak-hickory (51%) dominated by oak species and shagbark hickory. Maple-basswood forests (28%), dominated by sugar maple, basswood and red maple, are common in areas that were not subjected to repeated presettlement wildfires. Bottomland hardwoods (10%) are common in the valley bottoms of major rivers and are dominated by silver maple, ashes, elms, cottonwood, and red maple. Relict conifer forests including white pine, hemlock and yellow birch are a rarer natural community in the cooler, steep, north slope microclimates. The Central Sand Hills Ecological Landscape is located in central Wisconsin at the eastern edge of what was once Glacial Lake Wisconsin. The landforms in this Ecological Landscape are a series of glacial moraines that were later partially covered by glacial outwash. The area is characterized by a mixture of farmland, woodlots, wetlands, small kettle lakes, and cold water streams, all on sandy soils. The mosaic of glacial moraine and pitted outwash throughout this Ecological Landscape has given rise to extensive wetlands in the outwash areas, and the headwaters of coldwater streams that originate in glacial moraines. The growing season is long enough for agriculture but the sandy soils limit agricultural productivity somewhat. Historic upland vegetation consisted of oak-forest, oak savanna, and tallgrass prairie. Fens were common in this Ecological Landscape and occurred along with wet-mesic prairie, wet prairie, and rare coastal plain marshes. Current vegetation is composed of more than one-third agricultural crops, and almost 20% grasslands with smaller amounts of open wetland, open water, shrubs, barren, and urban areas. The major forested type is oak-hickory, with smaller amounts of white-red-jack pine, maple-basswood, lowland hardwoods, aspen-birch, and spruce-fir.

Date  2002

Recreational Opportunities

The Mazomanie and Black Hawk units of the Lower Wisconsin State Riverway lie in this watershed. The Mazomanie unit is 4,261 acres (only 3,518 are owned, the rest are leased). This unit has areas of marsh, potholes, forest, lake and stream and offers a variety of recreational opportunities from a dog training ground, Class I field trial grounds, fishing, canoeing, birdwatching, berry picking and hiking. The Black Hawk Unit is 800 acres of state owned land and has a historical site as well as opportunities to cross country ski, and birdwatch.

Date  2002

Wildlife and Habitat

The watershed is also home for a variety of rare plant and animal species including; 1 species of beetle, 3 species of birds, 3 species of butterflies, 3 species of dragonflies, 13 species of fish, 1 species of grasshopper, 3 species of moths, 8 species of mussels, 30 plant species, 3 species of snakes, 2 species of mammals and 1 species of lizard. These plants and animals are also listed on the state's Natural Heritage Inventory (NHI).

Date  2002

Watershed Documents
Watershed Grants
Grant Details
Aquatic Invasives Education
Date
10/1/2011
Waters Involved
Crystal Lake
Status
Complete

Dane County: Aquatic Mgmt Plan Amendment: Dane County Office of Lakes and Watersheds will update Aquatic Plant Management (APM) Plans on the following lakes: Crystal, Fish, Indian, Lower Mud, Upper Mud, and the Yahara River between Lakes Monona and Kegonsa. All these waters are sources of established populations of Eurasian watermilfoil, among other exotics, and are managed via county harvesting operations. In addition, the new Lake Belle View may require harvesting, so a new APM plan will be developed for that lake. Updated monitoring and amended plans are recommended by DNR for the other waters. A consultant will use established point intercept maps to survey current plant populations, and use those data to re-evaluate management plans, ensuring that the best management options are being implemented. Regular updates are presented in public meetings to Dane County staff and the Dane County Lakes and Watershed Commission. Updated plans are posted on the county website.


Grant Details
Aquatic Invasives Education
Date
10/1/2011
Waters Involved
Fish Lake
Status
Complete

Dane County: Aquatic Mgmt Plan Amendment: Dane County Office of Lakes and Watersheds will update Aquatic Plant Management (APM) Plans on the following lakes: Crystal, Fish, Indian, Lower Mud, Upper Mud, and the Yahara River between Lakes Monona and Kegonsa. All these waters are sources of established populations of Eurasian watermilfoil, among other exotics, and are managed via county harvesting operations. In addition, the new Lake Belle View may require harvesting, so a new APM plan will be developed for that lake. Updated monitoring and amended plans are recommended by DNR for the other waters. A consultant will use established point intercept maps to survey current plant populations, and use those data to re-evaluate management plans, ensuring that the best management options are being implemented. Regular updates are presented in public meetings to Dane County staff and the Dane County Lakes and Watershed Commission. Updated plans are posted on the county website.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Barbian Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Barbian Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Bass Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Bass Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Brandenburg Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Brandenburg Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Carl Buechner Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Carl Buechner Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Cherokee Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Cherokee Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Crystal Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Crystal Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Diedrich Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Diedrich Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
10/1/1999
Waters Involved
Fish Lake
Status
Complete

Natural Heritage Land Trust: Acq-Fish Lake Conservation Project: This grant will provide financial assistance for the acquisition of approximately 117 acres along Fish Lake, including approximately 1,600 feet of lakeshore frontage.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Fish Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Fish Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2006
Waters Involved
Fish Lake
Status
Complete

Dane County Parks: Acq-Fish And Mud Lakes-Marx Acquisition: The Marx property has already been purchased by Dane County. The property will protect the majority of the Mud Lake shoreline, which is connected to Fish Lake, a very important resource in NW Dane County. This land is adjacent to other property already purchased by the County. In five years, the property will be converted from row cropping to natural drainage patterns and natural vegetation to encourage wildlife and promote water quality benefits.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Fishers Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Fishers Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Goose Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Goose Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Graber Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Graber Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Grass Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Grass Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Hook Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Hook Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Indian Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Indian Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Island Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Island Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Kalscheur Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Kalscheur Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Barney
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Barney
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Belle View
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Belle View
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Harriett
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Harriett
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Kegonsa
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Kegonsa
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Koshkonong
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Koshkonong
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Mendota
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Mendota
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Monona
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Monona
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Waubesa
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Waubesa
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Wingra
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Wingra
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
5/25/1995
Waters Involved
Lake Wisconsin
Status
Complete

Town Of Lodi: Acq-Lake Wisconsin Okee Community Park Land Acquisition: The Town of Lodi proposes to acquire 8.5 acres of land in the Okee Bay area of Lake Wisconsin for recreational opportunities and lake protection. Eligible costs include acquisition of the parcel, appraisal fee and preparation of an environmental assessment.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Wisconsin
Status
Complete

Town Of Merrimac: Acq-Clingman Property Land Acquisition: The Town of Merrimac will purchase the Clingman Property on Lake Wisconsin in the County of Sauk (approx. 15.1 acres). The Town of Merrimac will comply with the approved Regional Management Plan.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Louis Buechner Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Louis Buechner Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Maher Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Maher Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Marshall Millpond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Marshall Millpond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Maunesha Flowage
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Maunesha Flowage
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Meier Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Meier Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Morse Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Morse Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Mortenson Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Mortenson Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Mud Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Mud Lake
Status
Complete

Dane County: Acq-Marcus Marx Property Acquisition: Dane County Parks Department will acquire 58 acres of land adjacent to Mud Lake in the Town of Roxbury in order to restore native vegetation and provide a permanent buffer that will filter upstream runoff before it enters Mud Lake and Fish Lakes. The acquisition of this property will protect the land and the waters from further degradation.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Mud Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Rice Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Rice Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Rockdale Millpond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Rockdale Millpond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Salmo Pond (Raemisch Pond)
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Salmo Pond (Raemisch Pond)
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Springfield Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Springfield Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Stebbinsville Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Stebbinsville Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Stewart Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Stewart Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Stoughton Millpond 429
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Stoughton Millpond 429
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Strickers Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Strickers Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Tenney Park Lagoon
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Tenney Park Lagoon
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Tiedemans Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Tiedemans Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Unnamed
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Unnamed
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Upper Mud Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Upper Mud Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Verona Gravel Pit
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Verona Gravel Pit
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Virgin Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Virgin Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Windsor Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Windsor Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Barbian Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Bass Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Brandenburg Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Carl Buechner Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
4/1/2010
Waters Involved
Castle Rock Ditch
Status
Complete

Lake Alice Association, Inc: Lake Alice Stewardship Program Phase Ii - Understanding The Biota Of Lake Alice: Lake Alice Association is sponsoring phased large scale lake planning grants to study Lake Alice, in Lincoln County. The project will focus on developing and updating an Adaptive Lake Management Plan (LMP) for Lake Alice. Phase 2 was funded in this grant cycle and Phases 3-5 will be submitted for funding starting in 2011.

Project activities for Phase 2 include: 1) Educational program, meetings and educational events with lake association and Tomahawk High School students, written educational materials, news releases, and website updates; 2) Point-intercept (PI) aquatic plant survey; 3) Aquatic plant community and substrate mapping; 4) Water quality assessment; 5) Volunteer amphibian monitoring and angler survey; 6) Update LMP.

Project deliverables include: 1) Educational materials and news releases; 2) Aquatic plant community and substrate maps; 3) PI, water quality, amphibian, and angler data; 4) LMP.

Specific conditions for this project: LMP needs Dept review and approval

WDNR Lakes Management Coordinator will be provided with an electronic (pdf or word) and hard copy of LMP, news releases, any other educational materials/products, all data, all maps from project, and all GIS data.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Cherokee Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
4/1/2010
Waters Involved
Cruson Slough
Status
Complete

Lake Alice Association, Inc: Lake Alice Stewardship Program Phase Ii - Understanding The Biota Of Lake Alice: Lake Alice Association is sponsoring phased large scale lake planning grants to study Lake Alice, in Lincoln County. The project will focus on developing and updating an Adaptive Lake Management Plan (LMP) for Lake Alice. Phase 2 was funded in this grant cycle and Phases 3-5 will be submitted for funding starting in 2011.

Project activities for Phase 2 include: 1) Educational program, meetings and educational events with lake association and Tomahawk High School students, written educational materials, news releases, and website updates; 2) Point-intercept (PI) aquatic plant survey; 3) Aquatic plant community and substrate mapping; 4) Water quality assessment; 5) Volunteer amphibian monitoring and angler survey; 6) Update LMP.

Project deliverables include: 1) Educational materials and news releases; 2) Aquatic plant community and substrate maps; 3) PI, water quality, amphibian, and angler data; 4) LMP.

Specific conditions for this project: LMP needs Dept review and approval

WDNR Lakes Management Coordinator will be provided with an electronic (pdf or word) and hard copy of LMP, news releases, any other educational materials/products, all data, all maps from project, and all GIS data.


Grant Details
Large Scale Lake Planning
Date
10/1/1999
Waters Involved
Crystal Lake
Status
Complete

Dane County: Crystal Lake Hydrologic Study: The objectives of this project are to: 1) Demonstrate an understanding of the hydrology of lake/groundwater system in the vicinity of Crystal, Fish, and Mud Lakes by simulating measured lake stage, groundwater elevation, and local stream flow. 2) Predict the possible effect of pumping water from Fish Lake on Crystal Lake stage.

A full description of project scope and product deliverables is available in the grant application, which is part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Crystal Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2005
Waters Involved
Crystal Lake
Status
Complete

Dane County: Preparation Of Apm Plans--Lower Mud, Fish, Crystal, Wingra & Indian Lakes: Aquatic plant and substrate surveys will be conducted, followed by evaluation of changes over time to develop or modify APM plans for these waters.


Grant Details
Large Scale Lake Planning
Date
4/1/2013
Waters Involved
Crystal Lake
Status
Complete

Dane County: Assessment Of Wq & Nearshore Fish Populations In Fish, Crystal And Mud Lakes: Dane County intends to sample water quality, algae, and near-shore fish populations, Fish, Mud and Crystal Lakes in northern Dane County. Baseline data are needed to help develop recreational use plans for a new county park in the area, and to document changes that have occurred since the lakes have been flooded since 2006 due to rising groundwater. The sampling frequency and protocol will also allow DNR partners to assess the lakes for possible 303d listing. Mud Lake will also be sampled for aquatic plants as a baseline inventory, as well as carp. The County will evaluate the possibility of doing carp control to help restore aquatic plants and cleaner water for the fishery. A final report including methods, findings and recommendations will be created and will be shared with District partners, the media and the DNR.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Diedrich Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
12/20/1990
Waters Involved
Fish Lake
Status
Complete

Dane County: Fish Lake Hydrology And Phosphorus Loading Evaluation: 1) Evaluate Fish Lake's hydrology and phophorus loading by lake stage and precipitation monitoring, estimation of surface runoff and lake evaporation, determination of groundwater flow, analysis of storm run-off, surface run-off, gorundwate, andprecipitation for total phosphorus; estimation of septic system outputs.


Grant Details
Large Scale Lake Planning
Date
10/11/1991
Waters Involved
Fish Lake
Status
Complete

Dane County: Fish Lake Usgs Hydrology And Phosphorus Loading Assessment: Data analysis and preparation of hydrologic and nutrient budget needed for diagnostic and feasibility study as described in the project proposal.Make management recommendations to improve lake water quality.Publish all data in USGS's annual data report 'Water Resources Data for Wisconsin'.Information will be disseminated to the public by newsletter, fact sheet, public meetings, summary report, and local newspaper articles.The final report will be reposited in Dane County libraries, the City-County Building, and the Roxbury Town Hall.


Grant Details
Large Scale Lake Planning
Date
10/1/1999
Waters Involved
Fish Lake
Status
Complete

Dane County: Fish Lake Hydrologic Study: The objectives of this project are to: 1) Demonstrate an understanding of the hydrology of lake/groundwater system in the vicinity of Fish, Crystal, and Mud Lakes by simulating measured lake stage, groundwater elevation, and local stream flow.

A full description of project scope and product deliverables is available in the grant application, which is part of this agreement.

The DNR will be provided with both a paper copy and an electronic copy of the final report. Information will be disseminated to the public as described in the grant application.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Fish Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2005
Waters Involved
Fish Lake
Status
Complete

Dane County: Preparation Of Apm Plans--Lower Mud, Fish, Crystal, Wingra & Indian Lakes: Aquatic plant and substrate surveys will be conducted, followed by evaluation of changes over time to develop or modify APM plans for these waters.


Grant Details
Large Scale Lake Planning
Date
4/1/2013
Waters Involved
Fish Lake
Status
Proposed

Dane County: Assessment Of Wq & Nearshore Fish Populations In Fish, Crystal And Mud Lakes: Dane County intends to sample water quality, algae, and near-shore fish populations, Fish, Mud and Crystal Lakes in northern Dane County. Baseline data are needed to help develop recreational use plans for a new county park in the area, and to document changes that have occurred since the lakes have been flooded since 2006 due to rising groundwater. The sampling frequency and protocol will also allow DNR partners to assess the lakes for possible 303d listing. Mud Lake will also be sampled for aquatic plants as a baseline inventory, as well as carp. The County will evaluate the possibility of doing carp control to help restore aquatic plants and cleaner water for the fishery. A final report including methods, findings and recommendations will be created and will be shared with District partners, the media and the DNR.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Fishers Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Goose Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Graber Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Grass Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Hook Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Indian Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Island Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Kalscheur Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Barney
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Belle View
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
4/1/2010
Waters Involved
Lake Du Bay
Status
Complete

Lake Alice Association, Inc: Lake Alice Stewardship Program Phase Ii - Understanding The Biota Of Lake Alice: Lake Alice Association is sponsoring phased large scale lake planning grants to study Lake Alice, in Lincoln County. The project will focus on developing and updating an Adaptive Lake Management Plan (LMP) for Lake Alice. Phase 2 was funded in this grant cycle and Phases 3-5 will be submitted for funding starting in 2011.

Project activities for Phase 2 include: 1) Educational program, meetings and educational events with lake association and Tomahawk High School students, written educational materials, news releases, and website updates; 2) Point-intercept (PI) aquatic plant survey; 3) Aquatic plant community and substrate mapping; 4) Water quality assessment; 5) Volunteer amphibian monitoring and angler survey; 6) Update LMP.

Project deliverables include: 1) Educational materials and news releases; 2) Aquatic plant community and substrate maps; 3) PI, water quality, amphibian, and angler data; 4) LMP.

Specific conditions for this project: LMP needs Dept review and approval

WDNR Lakes Management Coordinator will be provided with an electronic (pdf or word) and hard copy of LMP, news releases, any other educational materials/products, all data, all maps from project, and all GIS data.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Harriett
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Kegonsa
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Koshkonong
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Mendota
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Monona
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Waubesa
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Wingra
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/1999
Waters Involved
Lake Wisconsin
Status
Complete

Harmony Grove Lake Prot. And Rehab. District: Lake Wisconsin Harmony Grove Sediment Study: This project will investigate sediment in the Harmony Grove lagoons. The quantity of sediment will be determined through field measurements in the lagoons. Sediment samples will be collected and analyzed. Options for removal and disposal of the sediment will identified along with the costs associated with these options. Sediment inputs to the lagoons will also be evaluated and recommendations made to minimize future sedimentation. The information gathered in this study will be used to determine the need for future study or actions to support a lake management plan to protect the long term viability of the lagoons as a natural resource for fisheries and public recreation.

A full description of project scope and project deliverables is available in the grant application, which is a part of this agreement.

The DNR will be provided with both a paper copy and an electronic copy of the final report. Information will be disseminated to the public as described in the grant application.


Grant Details
Large Scale Lake Planning
Date
10/1/1999
Waters Involved
Lake Wisconsin
Status
Complete

Harmony Grove Lake Prot. And Rehab. District: Lake Wisconsin Harmony Grove Water Quality: Harmony Grove Lake Protection and Rehabilitation District will investigate water quality of the Harmony Grove lagoons. It will collect water quality data from the lagoons and Lake Wisconsin over a one year period. The impact of ground water flow to the lagoons will be determined. Pollution sources to the lagoons from the watershed will be identified and quantified. Recommendations will then be made to minimize the pollutant sources to the lagoons.

A full description of project scope and project deliverables is available in the grant application, which is part of this agreement.

The DNR will be provided with both a paper copy and an electronic copy of the final report. Information will be disseminated to the public as described in the grant application.


Grant Details
Large Scale Lake Planning
Date
4/1/2005
Waters Involved
Lake Wisconsin
Status
Complete

Harmony Grove Lake Prot. And Rehab. District: Apm & Sediment Management Plan For Harmony Grove Lake: The Harmony Grove Lake Protection and Rehabilitation District will monitor plants and sediments, summarize feasibility of all management options, and make recommendations for improving water quality.

A full description of project scope and deliverables is available in the grant application, which is part of this agreement. The DNR will be provided with both a paper copy and an electronic copy of the final report. Information will be disseminated to the public as described in the grant application.


Grant Details
Large Scale Lake Planning
Date
4/1/2005
Waters Involved
Lake Wisconsin
Status
Complete

Town Of West Point: Lake Wisconsin Organization Development And Town Of West Point Land Use Study: The West Point Township will explore land use planning options to preserve sensitive habitat and rural character of township, build partnerships, and begin collecting baseline data of local subwatershed, water quality and critical habitat.

A full description of project scope and deliverables is available in the grant application, which is part of this agreement. The DNR will be provided with both a paper copy and an electronic copy of the final report. Information will be desseminated to the public as described in the grant application.


Grant Details
Large Scale Lake Planning
Date
4/1/2010
Waters Involved
Little Pine Creek
Status
Complete

Lake Alice Association, Inc: Lake Alice Stewardship Program Phase Ii - Understanding The Biota Of Lake Alice: Lake Alice Association is sponsoring phased large scale lake planning grants to study Lake Alice, in Lincoln County. The project will focus on developing and updating an Adaptive Lake Management Plan (LMP) for Lake Alice. Phase 2 was funded in this grant cycle and Phases 3-5 will be submitted for funding starting in 2011.

Project activities for Phase 2 include: 1) Educational program, meetings and educational events with lake association and Tomahawk High School students, written educational materials, news releases, and website updates; 2) Point-intercept (PI) aquatic plant survey; 3) Aquatic plant community and substrate mapping; 4) Water quality assessment; 5) Volunteer amphibian monitoring and angler survey; 6) Update LMP.

Project deliverables include: 1) Educational materials and news releases; 2) Aquatic plant community and substrate maps; 3) PI, water quality, amphibian, and angler data; 4) LMP.

Specific conditions for this project: LMP needs Dept review and approval

WDNR Lakes Management Coordinator will be provided with an electronic (pdf or word) and hard copy of LMP, news releases, any other educational materials/products, all data, all maps from project, and all GIS data.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Louis Buechner Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Maher Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Marshall Millpond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Maunesha Flowage
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Meier Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Morse Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Mortenson Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
4/1/2001
Waters Involved
Mud Lake
Status
Complete

Dane County: Groundwater Lake Interactions - Crystal, Fish, Mud Lakes: This project will complete the work begun in projects LPL-666 and LPL-652 to: Demonstrate an understanding of the hydrology of lake/groundwater system in the vicinity of Crystal, Fish, and Mud lakes by simulating measured lake stage, groundwater elevation, and local stream flow; and predict the possible effect of pumping water from Fish Lake on Crystal Lake stage.

A full description of the project scope and deliverables is available in the grant application, which is part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Mud Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2005
Waters Involved
Mud Lake
Status
Complete

Dane County: Preparation Of Apm Plans--Lower Mud, Fish, Crystal, Wingra & Indian Lakes: Aquatic plant and substrate surveys will be conducted, followed by evaluation of changes over time to develop or modify APM plans for these waters.


Grant Details
Large Scale Lake Planning
Date
4/1/2013
Waters Involved
Mud Lake
Status
Proposed

Dane County: Assessment Of Wq & Nearshore Fish Populations In Fish, Crystal And Mud Lakes: Dane County intends to sample water quality, algae, and near-shore fish populations, Fish, Mud and Crystal Lakes in northern Dane County. Baseline data are needed to help develop recreational use plans for a new county park in the area, and to document changes that have occurred since the lakes have been flooded since 2006 due to rising groundwater. The sampling frequency and protocol will also allow DNR partners to assess the lakes for possible 303d listing. Mud Lake will also be sampled for aquatic plants as a baseline inventory, as well as carp. The County will evaluate the possibility of doing carp control to help restore aquatic plants and cleaner water for the fishery. A final report including methods, findings and recommendations will be created and will be shared with District partners, the media and the DNR.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Rice Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Rockdale Millpond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Salmo Pond (Raemisch Pond)
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Springfield Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Stebbinsville Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Stewart Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Stoughton Millpond 429
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Strickers Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Tenney Park Lagoon
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Tiedemans Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Unnamed
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2005
Waters Involved
Unnamed
Status
Complete

Dane County: Preparation Of Apm Plans--Lower Mud, Fish, Crystal, Wingra & Indian Lakes: Aquatic plant and substrate surveys will be conducted, followed by evaluation of changes over time to develop or modify APM plans for these waters.


Grant Details
Large Scale Lake Planning
Date
4/1/2010
Waters Involved
Unnamed
Status
Complete

Lake Alice Association, Inc: Lake Alice Stewardship Program Phase Ii - Understanding The Biota Of Lake Alice: Lake Alice Association is sponsoring phased large scale lake planning grants to study Lake Alice, in Lincoln County. The project will focus on developing and updating an Adaptive Lake Management Plan (LMP) for Lake Alice. Phase 2 was funded in this grant cycle and Phases 3-5 will be submitted for funding starting in 2011.

Project activities for Phase 2 include: 1) Educational program, meetings and educational events with lake association and Tomahawk High School students, written educational materials, news releases, and website updates; 2) Point-intercept (PI) aquatic plant survey; 3) Aquatic plant community and substrate mapping; 4) Water quality assessment; 5) Volunteer amphibian monitoring and angler survey; 6) Update LMP.

Project deliverables include: 1) Educational materials and news releases; 2) Aquatic plant community and substrate maps; 3) PI, water quality, amphibian, and angler data; 4) LMP.

Specific conditions for this project: LMP needs Dept review and approval

WDNR Lakes Management Coordinator will be provided with an electronic (pdf or word) and hard copy of LMP, news releases, any other educational materials/products, all data, all maps from project, and all GIS data.


Grant Details
Large Scale Lake Planning
Date
4/1/2013
Waters Involved
Unnamed
Status
Complete

Dane County: Assessment Of Wq & Nearshore Fish Populations In Fish, Crystal And Mud Lakes: Dane County intends to sample water quality, algae, and near-shore fish populations, Fish, Mud and Crystal Lakes in northern Dane County. Baseline data are needed to help develop recreational use plans for a new county park in the area, and to document changes that have occurred since the lakes have been flooded since 2006 due to rising groundwater. The sampling frequency and protocol will also allow DNR partners to assess the lakes for possible 303d listing. Mud Lake will also be sampled for aquatic plants as a baseline inventory, as well as carp. The County will evaluate the possibility of doing carp control to help restore aquatic plants and cleaner water for the fishery. A final report including methods, findings and recommendations will be created and will be shared with District partners, the media and the DNR.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Upper Mud Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Verona Gravel Pit
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Virgin Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Windsor Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
4/1/2010
Waters Involved
Wisconsin River
Status
Complete

Lake Alice Association, Inc: Lake Alice Stewardship Program Phase Ii - Understanding The Biota Of Lake Alice: Lake Alice Association is sponsoring phased large scale lake planning grants to study Lake Alice, in Lincoln County. The project will focus on developing and updating an Adaptive Lake Management Plan (LMP) for Lake Alice. Phase 2 was funded in this grant cycle and Phases 3-5 will be submitted for funding starting in 2011.

Project activities for Phase 2 include: 1) Educational program, meetings and educational events with lake association and Tomahawk High School students, written educational materials, news releases, and website updates; 2) Point-intercept (PI) aquatic plant survey; 3) Aquatic plant community and substrate mapping; 4) Water quality assessment; 5) Volunteer amphibian monitoring and angler survey; 6) Update LMP.

Project deliverables include: 1) Educational materials and news releases; 2) Aquatic plant community and substrate maps; 3) PI, water quality, amphibian, and angler data; 4) LMP.

Specific conditions for this project: LMP needs Dept review and approval

WDNR Lakes Management Coordinator will be provided with an electronic (pdf or word) and hard copy of LMP, news releases, any other educational materials/products, all data, all maps from project, and all GIS data.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Barbian Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Barbian Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Bass Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Bass Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Brandenburg Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Brandenburg Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Carl Buechner Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Carl Buechner Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Cherokee Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Cherokee Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Crystal Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Crystal Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Diedrich Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Diedrich Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Fish Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Fish Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Fishers Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Fishers Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Goose Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Goose Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Graber Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Graber Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Grass Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Grass Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Hook Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Hook Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Indian Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Indian Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Island Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Island Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Kalscheur Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Kalscheur Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Barney
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Barney
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Belle View
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Belle View
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Harriett
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Harriett
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Kegonsa
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Kegonsa
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Koshkonong
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Koshkonong
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Mendota
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Mendota
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Monona
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Monona
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Waubesa
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Waubesa
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Wingra
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Wingra
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2013
Waters Involved
Lake Wisconsin
Status
Complete

Columbia County Lwcd: Lake Wisconsin Access Inventory: Lake Wisconsin Access Inventory \2013 Columbia County LWCD will conduct a public access survey on the Columbia County side of Lake Wisconsin to help the public better use these areas and to help identify infrastructure needs, in addition to preparing for an eventual lake management plan that would include aquatic invasive species prevention component. After collecting property deed information, each public access site would be photographed, and a variety of parameters documented, including things like fire number, driving directions to the site, parking surface and number of spaces, signs posted, survey markers present, topography, etc. The data will be entered into a GEO database, and a final report will be presented to stakeholders.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Louis Buechner Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Louis Buechner Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Maher Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Maher Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Marshall Millpond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Marshall Millpond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Maunesha Flowage
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Maunesha Flowage
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Meier Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Meier Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Morse Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Morse Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Mortenson Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Mortenson Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Mud Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Mud Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Rice Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Rice Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Rockdale Millpond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Rockdale Millpond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Salmo Pond (Raemisch Pond)
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Salmo Pond (Raemisch Pond)
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Springfield Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Springfield Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Stebbinsville Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Stebbinsville Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Stewart Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Stewart Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Stoughton Millpond 429
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Stoughton Millpond 429
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Strickers Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Strickers Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Tenney Park Lagoon
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Tenney Park Lagoon
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Tiedemans Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Tiedemans Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Unnamed
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Unnamed
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Upper Mud Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Upper Mud Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Verona Gravel Pit
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Verona Gravel Pit
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Virgin Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Virgin Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Windsor Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Windsor Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2013
Waters Involved
Wisconsin River
Status
Complete

Columbia County Lwcd: Lake Wisconsin Access Inventory: Lake Wisconsin Access Inventory \2013 Columbia County LWCD will conduct a public access survey on the Columbia County side of Lake Wisconsin to help the public better use these areas and to help identify infrastructure needs, in addition to preparing for an eventual lake management plan that would include aquatic invasive species prevention component. After collecting property deed information, each public access site would be photographed, and a variety of parameters documented, including things like fire number, driving directions to the site, parking surface and number of spaces, signs posted, survey markers present, topography, etc. The data will be entered into a GEO database, and a final report will be presented to stakeholders.


Grant Details
River Planning Grant
Date
2/15/2015
Waters Involved
Lake Wisconsin
Status
Complete

Lake Wisconsin Alliance: Education And Awareness: Lake Wisconsin Alliance will undertake a River Planning Grant project that will expand outreach and education of Lake Wisconsin natural and recreational resources, and lake water quality issues. The goal is to increase membership, provide identity to the LWA, and inform citizens living within the Lake Wisconsin watershed.
Deliverables: 1. The Lake Wisconsin Alliance technical advisory team will provide action items to LWA members to help attain goals and objectives to protect and enhance L. Wisconsin. 2. Communicate the LWA mission and organizational roles through brochures and website development. 3. Develop a logo to give the alliance identity. 4. Website membership development to assist in expansion of membership, and develop a calendar of activites hosted by the alliance. 5. Host workshops and seminars to educate the public on lake water quality and strategies that help protect/enhance lake water quality.


Grant Details
River Planning Grant
Date
7/1/2004
Waters Involved
Wisconsin River
Status
Complete

Sauk Prairie River Projects Assoc. Ltd: Wisconsin River Restoration: Sauk Prairie River Projects Association LTD will organize existing groups, clubs, and organizations and will work with local and state agencies in order to develop a plan for the project area. That plan will involve local groups in understanding and protecting: river natural resources and features, the positive impact of these resources on the local economy, and the importance of river access and recreational opportunities. A full description of the project goals, objectives, methods, activities, products and deliverables is included in the grant application, which is a part of this grant contract.


Grant Details
River Planning Grant
Date
2/15/2015
Waters Involved
Wisconsin River
Status
Complete

Lake Wisconsin Alliance: Education And Awareness: Lake Wisconsin Alliance will undertake a River Planning Grant project that will expand outreach and education of Lake Wisconsin natural and recreational resources, and lake water quality issues. The goal is to increase membership, provide identity to the LWA, and inform citizens living within the Lake Wisconsin watershed.
Deliverables: 1. The Lake Wisconsin Alliance technical advisory team will provide action items to LWA members to help attain goals and objectives to protect and enhance L. Wisconsin. 2. Communicate the LWA mission and organizational roles through brochures and website development. 3. Develop a logo to give the alliance identity. 4. Website membership development to assist in expansion of membership, and develop a calendar of activites hosted by the alliance. 5. Host workshops and seminars to educate the public on lake water quality and strategies that help protect/enhance lake water quality.


Monitoring & Projects

Projects including grants, restoration work and studies shown below have occurred in this watershed. Click the links below to read through the text. While these are not an exhaustive list of activities, they provide insight into the management activities happening in this watershed.

Grants and Management Projects
Roxbury Creek Watershed
Watershed Recommendations
Hire County Aquatic Invasives Coordinator
 
Date
Status
Hire Aquatic Invasives (AIS) County Coordinator - Columbia
1/1/2011
In Progress
Projects
 
Monitor Aquatic Biology
Marsh Creek (wbic: 1252900)
Date
Status
This water (1252900, Marsh Creek, AU: 13346) was assessed for the 2016 integrated reporting process and found to have clearly meeting total phosphorus but poor biology (either fish or macroinvertebrates) (see parameter assessment results). Follow up monitoring should be conducted to clarify the status of biology in the water.
7/30/2015
Proposed
Projects
 
Roxbury Creek WatershedWatershed History Note

The Town of Roxbury is located in the Roxbury Creek Watershed. The town's growth was connected to the arrival of Agoston Haraszthy, a colorful nobleman and political refugee from Hungary. By 1841, he had purchased a large parcel of land where Sauk City now stands. He also built a hunting lodge, opposite his home, on a bluff in Roxbury overlooking the river. For the next several years, Haraszthy was active as a trader, hunter, steamboat operator, and viticulturist, and his business activities attracted attention to the area. He established a ferry that crossed the river, connecting Roxbury with Sauk City (then named "Haraszthy"). In 1841, Robert Richards and Jacob Fraelich, the ferry operators, became the first settlers in Roxbury after Haraszthy. Haraszthy's vineyards were located on a scenic hillside overlooking the Wisconsin River. Following several years of disappointment with winter damage on his vines and unfortunate politics, Haraszthy followed the gold rush west in 1849 and eventually became known as the founder of the California wine industry. Back in Roxbury, Peter Kehl took over the vineyards and planted conventional grape varieties, which he buried every year to protect them from Wisconsin's winters. The winery stayed in the family until 1899 when the farm was then converted to farm more conventional crops. But in 1972, the nearly abandoned property was purchased by the Wollersheim family who replanted the vines and brought the vineyards and wine business to a new level of success and national recognition.

Date  2011