Watershed - Little Rib River (CW24)
Little Rib River Watershed

Details

The Little Rib River Watershed is located in the Marathon and Lincoln Counties. Steep slopes and shallow soils characterize the Little Rib River Watershed. Stream flows vary significantly depending on the gradient of the slopes. During runoff events, elevated levels of bacteria and BOD occur in watershed streams, likely from animal waste (Kaatz, 1987, 1988). Both the Marathon County Animal Waste Management Plan and Soil Erosion Control Plan identify the Little Rib River as a priority for soil erosion and animal waste control. The potential for surface and groundwater contamination is high because steep slopes, shallow soils and bedrock that is within five feet of the surface, characterize the area. This watershed has been chosen as a priority watershed project under the Wisconsin Farmers Fund for animal waste control. This watershed was ranked using the Nonpoint Source Priority Watershed Selection Criteria. Based on surface and ground water data, the overall ranking is medium, establishing a priority for future grant eligibility through the Nonpoint Source Program. Marathon County's Land Conservation Department estimates that there are approximately 350 earthen manure pits installed prior to adoption of Marathon County's animal waste storage ordinance. Many of these pits may not meet technical standards and could potentially contaminate groundwater (Kaatz, 1987,1988).

Date  2002

Ecological Landscapes for Little Rib River Watershed

Ecological Landscapes

The Little Rib River Watershed is located in the Forest Transition Ecological Landscape which lies along the northern border of Wisconsin's Tension Zone, through the central and western part of the state, and supports both northern forests and agricultural areas. The central portion of the Forest Transition lies primarily on a glacial till plain deposited by glaciation between 25,000 and 790,000 years ago. The eastern and western portions are on moraines of the Wisconsin glaciation. The growing season in this part of the state is long enough that agriculture is viable, although climatic conditions are not as favorable as in southern Wisconsin. Soils are diverse, ranging from sandy loam to loam or shallow silt loam, and from poorly drained to well drained. The historic vegetation of the Forest Transition was primarily northern hardwood forest. These northern hardwoods were dominated by sugar maple and hemlock, and contained some yellow birch, red pine and white pine. Currently, over 60% of this Ecological Landscape is non-forested. Forested areas consist primarily of northern hardwoods and aspen, with smaller amounts of oak and lowland hardwoods. The eastern portion of the Ecological Landscape differs from the rest of the area in that it remains primarily forested, and includes some ecologically significant areas. Throughout the Ecological Landscape, small areas of conifer swamp are found near the headwaters of streams, and associated with lakes in kettle depressions on moraines. Ground flora show characteristics of both northern and southern Wisconsin, as this Ecological Landscape lies along the Tension Zone.

Date  2010

Watershed Grants
Grant Details
Large Scale Lake Planning
Date
4/1/2010
Waters Involved
Castle Rock Ditch
Status
Complete

Lake Alice Association, Inc: Lake Alice Stewardship Program Phase Ii - Understanding The Biota Of Lake Alice: Lake Alice Association is sponsoring phased large scale lake planning grants to study Lake Alice, in Lincoln County. The project will focus on developing and updating an Adaptive Lake Management Plan (LMP) for Lake Alice. Phase 2 was funded in this grant cycle and Phases 3-5 will be submitted for funding starting in 2011.

Project activities for Phase 2 include: 1) Educational program, meetings and educational events with lake association and Tomahawk High School students, written educational materials, news releases, and website updates; 2) Point-intercept (PI) aquatic plant survey; 3) Aquatic plant community and substrate mapping; 4) Water quality assessment; 5) Volunteer amphibian monitoring and angler survey; 6) Update LMP.

Project deliverables include: 1) Educational materials and news releases; 2) Aquatic plant community and substrate maps; 3) PI, water quality, amphibian, and angler data; 4) LMP.

Specific conditions for this project: LMP needs Dept review and approval

WDNR Lakes Management Coordinator will be provided with an electronic (pdf or word) and hard copy of LMP, news releases, any other educational materials/products, all data, all maps from project, and all GIS data.


Grant Details
Large Scale Lake Planning
Date
4/1/2010
Waters Involved
Cruson Slough
Status
Complete

Lake Alice Association, Inc: Lake Alice Stewardship Program Phase Ii - Understanding The Biota Of Lake Alice: Lake Alice Association is sponsoring phased large scale lake planning grants to study Lake Alice, in Lincoln County. The project will focus on developing and updating an Adaptive Lake Management Plan (LMP) for Lake Alice. Phase 2 was funded in this grant cycle and Phases 3-5 will be submitted for funding starting in 2011.

Project activities for Phase 2 include: 1) Educational program, meetings and educational events with lake association and Tomahawk High School students, written educational materials, news releases, and website updates; 2) Point-intercept (PI) aquatic plant survey; 3) Aquatic plant community and substrate mapping; 4) Water quality assessment; 5) Volunteer amphibian monitoring and angler survey; 6) Update LMP.

Project deliverables include: 1) Educational materials and news releases; 2) Aquatic plant community and substrate maps; 3) PI, water quality, amphibian, and angler data; 4) LMP.

Specific conditions for this project: LMP needs Dept review and approval

WDNR Lakes Management Coordinator will be provided with an electronic (pdf or word) and hard copy of LMP, news releases, any other educational materials/products, all data, all maps from project, and all GIS data.


Grant Details
Large Scale Lake Planning
Date
4/1/2010
Waters Involved
Lake Du Bay
Status
Complete

Lake Alice Association, Inc: Lake Alice Stewardship Program Phase Ii - Understanding The Biota Of Lake Alice: Lake Alice Association is sponsoring phased large scale lake planning grants to study Lake Alice, in Lincoln County. The project will focus on developing and updating an Adaptive Lake Management Plan (LMP) for Lake Alice. Phase 2 was funded in this grant cycle and Phases 3-5 will be submitted for funding starting in 2011.

Project activities for Phase 2 include: 1) Educational program, meetings and educational events with lake association and Tomahawk High School students, written educational materials, news releases, and website updates; 2) Point-intercept (PI) aquatic plant survey; 3) Aquatic plant community and substrate mapping; 4) Water quality assessment; 5) Volunteer amphibian monitoring and angler survey; 6) Update LMP.

Project deliverables include: 1) Educational materials and news releases; 2) Aquatic plant community and substrate maps; 3) PI, water quality, amphibian, and angler data; 4) LMP.

Specific conditions for this project: LMP needs Dept review and approval

WDNR Lakes Management Coordinator will be provided with an electronic (pdf or word) and hard copy of LMP, news releases, any other educational materials/products, all data, all maps from project, and all GIS data.


Grant Details
Large Scale Lake Planning
Date
4/1/2012
Waters Involved
Lake Wausau
Status
Complete

Lake Wausau Assn., Inc.: Wausau Mgmt. Plan 1: The Lake Wausau Association proposes to contract with the Army Corps of Engineers (ACE) to initiate studies toward development of a comprehensive Lake Management Plan for Lake Wausau in Marathon County. Phase 1 tasks to include: 1) Hydrodynamic Modeling, 2) Dye Tracer Studies, 3) Aquatic Macrophyte Survey and Aquatic Plant Management Plan, 4) Bathymetry and In-Lake Habitat assessment.


Grant Details
Large Scale Lake Planning
Date
10/1/2012
Waters Involved
Lake Wausau
Status
Complete

Lake Wausau Assn., Inc.: Wausau Management Plan 2: The Lake Wausau Association proposes to continue its contract with the Army Corps of Engineers (ACE) to initiate studies toward development of a comprehensive Lake Management Plan for Lake Wausau in Marathon County. Phase 2 tasks to include: 1) Hydrodynamic Modeling, 2) Dye Tracer Studies, 3) Socio-economic study, and 4) Project management and coordination.

Scope amendment: Add lake management plan development to the project


Grant Details
Large Scale Lake Planning
Date
4/1/2013
Waters Involved
Lake Wausau
Status
Complete

Lake Wausau Assn., Inc.: Wausau Mgmt. Plan 3: The Lake Wausau Association proposes to complete tasks Phase 3, Tasks 1, 5, and 7 of its comprehensive lake management planning effort on Lake Wausau in Marathon County. Major project elements to include: 1) Hydrodynamic modeling, 2) Shoreland habitat survey, and 3) Development of Lake Management Plan.


Grant Details
Large Scale Lake Planning
Date
4/1/2010
Waters Involved
Little Pine Creek
Status
Complete

Lake Alice Association, Inc: Lake Alice Stewardship Program Phase Ii - Understanding The Biota Of Lake Alice: Lake Alice Association is sponsoring phased large scale lake planning grants to study Lake Alice, in Lincoln County. The project will focus on developing and updating an Adaptive Lake Management Plan (LMP) for Lake Alice. Phase 2 was funded in this grant cycle and Phases 3-5 will be submitted for funding starting in 2011.

Project activities for Phase 2 include: 1) Educational program, meetings and educational events with lake association and Tomahawk High School students, written educational materials, news releases, and website updates; 2) Point-intercept (PI) aquatic plant survey; 3) Aquatic plant community and substrate mapping; 4) Water quality assessment; 5) Volunteer amphibian monitoring and angler survey; 6) Update LMP.

Project deliverables include: 1) Educational materials and news releases; 2) Aquatic plant community and substrate maps; 3) PI, water quality, amphibian, and angler data; 4) LMP.

Specific conditions for this project: LMP needs Dept review and approval

WDNR Lakes Management Coordinator will be provided with an electronic (pdf or word) and hard copy of LMP, news releases, any other educational materials/products, all data, all maps from project, and all GIS data.


Grant Details
Large Scale Lake Planning
Date
4/1/2010
Waters Involved
Unnamed
Status
Complete

Lake Alice Association, Inc: Lake Alice Stewardship Program Phase Ii - Understanding The Biota Of Lake Alice: Lake Alice Association is sponsoring phased large scale lake planning grants to study Lake Alice, in Lincoln County. The project will focus on developing and updating an Adaptive Lake Management Plan (LMP) for Lake Alice. Phase 2 was funded in this grant cycle and Phases 3-5 will be submitted for funding starting in 2011.

Project activities for Phase 2 include: 1) Educational program, meetings and educational events with lake association and Tomahawk High School students, written educational materials, news releases, and website updates; 2) Point-intercept (PI) aquatic plant survey; 3) Aquatic plant community and substrate mapping; 4) Water quality assessment; 5) Volunteer amphibian monitoring and angler survey; 6) Update LMP.

Project deliverables include: 1) Educational materials and news releases; 2) Aquatic plant community and substrate maps; 3) PI, water quality, amphibian, and angler data; 4) LMP.

Specific conditions for this project: LMP needs Dept review and approval

WDNR Lakes Management Coordinator will be provided with an electronic (pdf or word) and hard copy of LMP, news releases, any other educational materials/products, all data, all maps from project, and all GIS data.


Grant Details
Large Scale Lake Planning
Date
4/1/2010
Waters Involved
Wisconsin River
Status
Complete

Lake Alice Association, Inc: Lake Alice Stewardship Program Phase Ii - Understanding The Biota Of Lake Alice: Lake Alice Association is sponsoring phased large scale lake planning grants to study Lake Alice, in Lincoln County. The project will focus on developing and updating an Adaptive Lake Management Plan (LMP) for Lake Alice. Phase 2 was funded in this grant cycle and Phases 3-5 will be submitted for funding starting in 2011.

Project activities for Phase 2 include: 1) Educational program, meetings and educational events with lake association and Tomahawk High School students, written educational materials, news releases, and website updates; 2) Point-intercept (PI) aquatic plant survey; 3) Aquatic plant community and substrate mapping; 4) Water quality assessment; 5) Volunteer amphibian monitoring and angler survey; 6) Update LMP.

Project deliverables include: 1) Educational materials and news releases; 2) Aquatic plant community and substrate maps; 3) PI, water quality, amphibian, and angler data; 4) LMP.

Specific conditions for this project: LMP needs Dept review and approval

WDNR Lakes Management Coordinator will be provided with an electronic (pdf or word) and hard copy of LMP, news releases, any other educational materials/products, all data, all maps from project, and all GIS data.


Grant Details
Large Scale Lake Planning
Date
4/1/2013
Waters Involved
Wisconsin River
Status
Complete

Lake Wausau Assn., Inc.: Wausau Mgmt. Plan 3: The Lake Wausau Association proposes to complete tasks Phase 3, Tasks 1, 5, and 7 of its comprehensive lake management planning effort on Lake Wausau in Marathon County. Major project elements to include: 1) Hydrodynamic modeling, 2) Shoreland habitat survey, and 3) Development of Lake Management Plan.


Monitoring & Projects

Projects including grants, restoration work and studies shown below have occurred in this watershed. Click the links below to read through the text. While these are not an exhaustive list of activities, they provide insight into the management activities happening in this watershed.

Little Rib River Watershed
Watershed Recommendations
Citizen-Based Stream Monitoring
Citizen Stream Monitoring
Date
Status
Collect chemical, physical, and/or biological water quality data to assess the current overall stream health. The data can inform management decisions and may be used to identify impaired waters for biennial lists.
1/1/2012
In Progress
Projects
 