Electric Transmission Lines

Arrowhead-Weston Transmission Line

After a formal contested case hearing in May and June of 2005, the Administrative Law Judge approved the Department´s wetland and waterway crossing permit [PDF file] on July 25, 2005 for the Arrowhead-Weston transmission line project [exit DNR].

For each of the 9 total spreads, the Wisconsin DNR and PSCW must approve a Construction and Mitigation plan (CMP-B). The CMP-B is a key permit requirement of the wetland and waterway crossing permit approved by the Administrative Law Judge. No work may begin on any spread until the CMP-B is approved.

Drafts of these documents will be available for public review on the project Web site [exit DNR] and at local libraries along the route. The final approved CMP-B for each spread will also be on the project Web site [exit DNR].

Construction is expected to proceed from south to north, though work will occur at multiple locations at any one time. Construction oversight will occur at several layers.

CMP-B Approvals

  • Spread WW - Marathon County - August 5, 2005
  • Spread LW - Marathon & Clark Counties - August 5, 2005
  • Spread CL - Clark, Chippewa, & Taylor Counties - October 31, 2005
  • Spread BC - Rusk County - January 13, 2006
  • Spread MS - Sawyer & Washburn Counties - May 8, 2006
  • Spread SB - Rusk & Sawyer Counties - May 11, 2006
  • Spread AL - Douglas County - September 13, 2006
  • Spread HM - Douglas County - December 8, 2006
  • Spread LH - Douglas County - January 10, 2007

Some Other Key Milestones

Requirements for Power Line and Power Plant Development [exit DNR]