Wisconsin Department of Natural Resources

11 Steps General Overview of Construction Permit Process - WDNR

Step 2

Is A Permit Required?

The facility needs to answer several questions about their emissions such as:

From there, they can determine if they are a major source* or a minor source which will help determine if a permit is needed and which type of permit is required. The Wisconsin Department of Commerce*, The Wisconsin DNR Permit Primer* or consulting firms are resources available to help answer the question, "Do we need a permit?"

Step 2

* Close window and see Reference Links on overview page.

11 Steps Overview

Last Review Date: April, 2007
Next Review Date: April, 2008

Last Revised: Thursday September 17 2009